Delayed off-plan projects in Dubai

225 active projects in Dubai are past the planned completion date registered with Dubai Land Department, and 477 more are behind their construction plan with that date still ahead. Overdue projects average 64.2% complete at their last DLD inspection and are a median 6 months past their planned date. Updated daily from DLD open data.

Past planned handover225
Behind plan, date ahead477
Overdue: average progress64.2%
Overdue: median delay6 mo

Past their planned handover 225

Still under construction after the completion date registered with Dubai Land Department, longest overdue first.

ProjectDeveloperDLD-inspected progressInspectedPlanned completionStatus
South Living
South LivingDubai South
DUBAI SOUTH PROPERTIES DWC LLC
88.83%
28 Jul 20265 Feb 2020Overdue · 80 mo
LIVING LEGENDS PHASE 7Living Legends
Tanmiyat Global Real Estate Development L L C
91.88%
27 Jan 202230 Sept 2021Overdue · 60 mo
SHERENA RESIDENCE 2
SHERENA RESIDENCE 2Majan
Rose Homes Investment (L.L.C)
82.03%
22 Apr 202631 Aug 2022Overdue · 49 mo
EDEN GARDEN
EDEN GARDENDubai Sports City
Lokhandwala Builders International Limited
96.02%
14 Jul 202331 Aug 2022Overdue · 49 mo
PALMAROSA
PALMAROSAPalmarosa
Gulf Developers Fzc
97.79%
8 Jan 202631 Oct 2022Overdue · 47 mo
ARYENE GREENS
ARYENE GREENSArjan
Diamond Star Real Estate Development L.L.C
80.13%
2 Apr 202630 Nov 2022Overdue · 46 mo
THE WIND TOWER I
THE WIND TOWER IJLT
H A B N Real Estate Development L.L.C
74.58%
10 Aug 20235 Jun 2023Overdue · 40 mo
THE WIND TOWER II
THE WIND TOWER IIJLT
H A B N Real Estate Development L.L.C
84.54%
10 Aug 20235 Jun 2023Overdue · 40 mo
Discovery Dunes
Discovery DunesMadinat Al Mataar
Dlc Ds Developer
70%
—1 Dec 2023Overdue · 34 mo
Luxury Family Residence
Luxury Family ResidenceJVC
Kappa Acca Real Estate Development
75.95%
25 Apr 202631 Dec 2023Overdue · 33 mo
Mars Residences
Mars ResidencesDubai Sports City
Mars Star Real Estate Development L.L.C
79.91%
5 Aug 202623 Mar 2024Overdue · 31 mo
DAMAC LAGOONS - LAGOON VIEWS 8
DAMAC LAGOONS - LAGOON VIEWS 8Al Hebiah Fifth
ISLAND OASIS PROPERTIES
41.45%
17 Aug 20265 Jul 2024Overdue · 27 mo
DAMAC HILLS - GEMS ESTATES 2
DAMAC HILLS - GEMS ESTATES 2
DAMAC CRESCENT PROPERTIES
62.64%
14 Apr 202615 Sept 2024Overdue · 25 mo
Casa Serene
Casa SereneSobha Heartland
Altus Properties Development L.L.C
73.97%
13 Jul 20262 Dec 2024Overdue · 22 mo
Azizi Grand
Azizi GrandDubai Sports City
AZIZI DEVELOPMENTS L.L.C
82.06%
24 Jun 20262 Feb 2025Overdue · 20 mo
Azizi Riviera Reve
Azizi Riviera ReveMeydan One
AZIZI DEVELOPMENTS L.L.C
76.57%
1 Jul 20265 Feb 2025Overdue · 20 mo
LIVING LEGENDS PHASE 5
LIVING LEGENDS PHASE 5Living Legends
Amer Alghurair Real Estate Development Co. L.L.C
48.89%
13 Apr 202631 Mar 2025Overdue · 18 mo
Elysian Mansions
Elysian MansionsAl Hebiah Fourth
MAJID AL FUTTAIM TILAL AL GHAF PHASE A L.L.C
93%
6 Aug 202631 Mar 2025Overdue · 18 mo
7 PARK CENTRAL BY METEORA
7 PARK CENTRAL BY METEORAJVC
METEORA REAL ESTATE DEVELOPMENT L.L.C
90.18%
14 Feb 202530 Apr 2025Overdue · 17 mo
ONE CANAL
ONE CANALDubai Water Canal
A H S Canal Development L.L.C
77.42%
28 Jul 202630 May 2025Overdue · 17 mo
CAVALLI COUTURE
CAVALLI COUTUREDubai Water Canal
Damac Business Real Estate Co. L.L.C
19.7%
8 Apr 202631 May 2025Overdue · 16 mo
Vincitore Volare
Vincitore VolareArjan
Vincitore Premium Real Estate Development L.L.C
63.38%
22 Apr 20261 Jun 2025Overdue · 16 mo
DAMAC LAGOONS - PORTOFINO
DAMAC LAGOONS - PORTOFINOAl Hebiah Fifth
ISLAND OASIS PROPERTIES
97.14%
16 Jul 202629 Jun 2025Overdue · 16 mo
Luxury Family Residence III
Luxury Family Residence IIIBusiness Bay
Kappa Acca Real Estate Development
50.6%
7 May 202630 Jun 2025Overdue · 15 mo
ZAYA ZUHA ISLAND
ZAYA ZUHA ISLANDThe World
Zaya Zuha Island For Real Estate Development L.L.C
81.1%
31 Jul 202530 Jun 2025Overdue · 15 mo
TRIA BY DEYAAR
TRIA BY DEYAARDSO
DEYAAR DEVELOPMENT (P.J.S.C)
94.11%
25 Aug 202630 Jun 2025Overdue · 15 mo
California Village
California VillageWadi Al Safa 4
Gfh Real Estate L.L.C
95.07%
8 May 202615 Jul 2025Overdue · 15 mo
DAMAC LAGOONS - NICE 2
DAMAC LAGOONS - NICE 2Al Hebiah Fifth
ISLAND OASIS PROPERTIES
83.88%
17 Aug 202629 Jul 2025Overdue · 15 mo
DAMAC LAGOONS - NICE 1
DAMAC LAGOONS - NICE 1Al Hebiah Fifth
ISLAND OASIS PROPERTIES
93.71%
10 Aug 202629 Jul 2025Overdue · 15 mo
CHIC TOWER
CHIC TOWERBusiness Bay
Pax Investment L.L.C
84.01%
17 Aug 202630 Jul 2025Overdue · 15 mo

Behind plan, handover still ahead 477

More than 25 percentage points below the progress their registered timeline expects at the last DLD inspection, soonest planned completion first.

ProjectDeveloperDLD-inspected progressInspectedPlanned completionStatus
Capital Horizon Terraces
Capital Horizon TerracesPalm Deira
CAPITAL INTERNATIONAL REAL ESTATE DEVELOPER L.L.C
4.41%
15 Sept 202630 Oct 2026Behind plan
Whitestone Residence
Whitestone ResidenceAl Satwa
AXIOM PRIME REAL ESTATE DEVELOPMENT L.L.C
3.04%
6 Jul 202631 Oct 2026Behind plan
Binghatti Aquarise
Binghatti AquariseBusiness Bay
Binghatti Developers FZE
21.04%
14 May 202631 Oct 2026Behind plan
California 2 by SD
California 2 by SDJabal Ali First
SAMANA STAR REAL ESTATE DEVELOPMENT L.L.C
33.67%
9 Sept 202631 Oct 2026Behind plan
Soho The Berkeley
Soho The BerkeleyDubai Hills
SOHO DEVELOPMENT L.L.C
46.03%
23 Sept 202631 Oct 2026Behind plan
A 99
A 99Dubai Land Residence Complex
ARABIAN GULF PROPERTIES
47.83%
19 Oct 202631 Oct 2026Behind plan
MAR CASA
MAR CASADubai Maritime City
DEYAAR DEVELOPMENT (P.J.S.C)
56.45%
4 Aug 202631 Oct 2026Behind plan
AG CENTRAL
AG CENTRALDubai Land Residence Complex
AG PROPERTIES L.L.C
58.65%
17 Sept 202631 Oct 2026Behind plan
Manhattan 2 by SD
Manhattan 2 by SDJVC
SAMANA STAR REAL ESTATE DEVELOPMENT L.L.C
21.24%
17 Sept 20261 Nov 2026Behind plan
AURA PRESTIGE
AURA PRESTIGEDSO
AURA INFINITE REAL ESTATE DEVELOPMENT L.L.C
40.06%
1 Oct 20261 Nov 2026Behind plan
MAS Barsha Residency
MAS Barsha ResidencyAl Barsha First
M A S REAL ESTATE DEVELOPMENT L.L.C
26.34%
3 Aug 202621 Nov 2026Behind plan
VIVID TOWER
VIVID TOWERJVT
OBJ1 REAL ESTATE DEVELOPMENT L.L.C
12.31%
12 Aug 202630 Nov 2026Behind plan
SEA LEGEND ONE BY MVS REAL ESTATE
SEA LEGEND ONE BY MVS REAL ESTATEPalm Deira
M V S REAL ESTATE DEVELOPMENT L.L.C
22.2%
4 Aug 202630 Nov 2026Behind plan
DAMAC HILLS - GEMS ESTATES 1
DAMAC HILLS - GEMS ESTATES 1Al Hebiah Third
DAMAC CRESCENT PROPERTIES
42.35%
1 Oct 202630 Nov 2026Behind plan
Trinity By Karma
Trinity By KarmaArjan
KARMA REALTY DEVELOPERS L.L.C
30.87%
30 Sept 20261 Dec 2026Behind plan
Bhuvi ResidenceMadinat Al Mataar
BRAVIMA REAL ESTATE DEVELOPMENT L.L.C
31.55%
6 Aug 202615 Dec 2026Behind plan
Lusin Residences by Ermax DevelopmentInternational City Ph 1
ERMAX DEVELOPMENT L.L.C
35.03%
18 Jun 202615 Dec 2026Behind plan
Olivia Residences
Olivia ResidencesDubai Investment Park First
KARMA REAL ESTATE DEVELOPMENT L.L.C
38.2%
21 Sept 202624 Dec 2026Behind plan
Eden Hills
Eden HillsHadaeq Sheikh Mohammed Bin Rashid
EDEN HILLS L.L.C
3.54%
22 Sept 202625 Dec 2026Behind plan
Seaside by Prestige One
Seaside by Prestige OnePalm Deira
PRESTIGE THE SEASIDE REAL ESTATE DEVELOPMENT L.L.C
43.03%
30 Jul 202625 Dec 2026Behind plan
Cove Edition Residence 3 By Imtiaz
Cove Edition Residence 3 By ImtiazDubai Land Residence Complex
IMTIAZ REAL ESTATE INVESTMENT & DEVELOPMENT L.L.C
43.99%
26 Oct 202625 Dec 2026Behind plan
Beach Walk Grand By Imtiaz
Beach Walk Grand By ImtiazPalm Deira
IMTIAZ BWG REAL ESTATE DEVELOPMENT L.L.C
53.22%
10 Aug 202625 Dec 2026Behind plan
LAYA COURTYARD
LAYA COURTYARDDubai Studio City
LAYA DEVELOPERS L.L.C
50.57%
15 Sept 202626 Dec 2026Behind plan
Baccarat Hotel and Residences, Dubai
Baccarat Hotel and Residences, DubaiBurj Khalifa
BC RESIDENCES L.L.C
21.16%
3 Sept 202629 Dec 2026Behind plan
EVERGRIN HOUSE 2
EVERGRIN HOUSE 2Al Satwa
OBJ1 REAL ESTATE DEVELOPMENT L.L.C
10.29%
21 Jul 202630 Dec 2026Behind plan
Al Haseen Residence 4
Al Haseen Residence 4Dubai Industrial City
DUGASTA PROPERTIES DEVELOPMENT L.L.C
11.76%
14 Jul 202630 Dec 2026Behind plan
Beachfront Gates 2Madinat Al Mataar
DUBAI SOUTH PROPERTIES DWC LLC
41.73%
14 Jul 202630 Dec 2026Behind plan
Moonsa Residences 2
Moonsa Residences 2International City Ph 2 & 3
DUGASTA PROPERTIES DEVELOPMENT L.L.C
1.01%
20 Jul 202631 Dec 2026Behind plan
Beverly Grande
Beverly GrandeMotor City
H M B HOMES REAL ESTATE DEVELOPMENT
2.27%
29 Sept 202631 Dec 2026Behind plan
Vio Residences
Vio ResidencesInternational City Ph 2 & 3
MODELUX REAL ESTATE DEVELOPMENT L.L.C
6.43%
3 Aug 202631 Dec 2026Behind plan

Developers with the most delayed projects

  1. AZIZI DEVELOPMENTS L.L.C22
  2. Binghatti Developers FZE20
  3. ISLAND OASIS PROPERTIES14
  4. THE PALM - JEBEL ALI CO. (L.L.C)14
  5. OBJ1 REAL ESTATE DEVELOPMENT L.L.C13
  6. ELLINGTON PROPERTIES DEVELOPMENT L.L.C10
  7. IMTIAZ REAL ESTATE INVESTMENT & DEVELOPMENT L.L.C9
  8. DAMAC ELITE INVESTMENT CO. L.L.C8

Delayed projects in Dubai: common questions

How many off-plan projects in Dubai are delayed?

225 active projects are past the planned completion date registered with Dubai Land Department, and 477 more are behind their construction plan. The most affected areas are JVC (80), Palm Deira (71), Dubai Land Residence Complex (43).

How do I check if a Dubai project is delayed?

Compare the project's DLD-inspected construction percentage with the planned completion date registered with Dubai Land Department. A project still below 100% after that date is overdue. Every project page on this site shows both figures with the date of the last inspection; the Dubai REST app shows the official status too.

What does 'behind plan' mean?

The DLD-inspected percentage is compared with the progress expected from the project's registered start and planned completion dates at the time of the inspection. More than 25 percentage points short counts as behind plan. It does not mean the project is cancelled.

What can I do if my project's handover is delayed?

Ask the developer for the revised schedule in writing, check the project's status with Dubai Land Department (for example in the Dubai REST app), and review the completion and delay clauses in your sale and purchase agreement. Developers and escrow accounts are regulated by RERA, DLD's regulatory arm. This site is informational, not legal advice.

How often is this list updated?

Every day, from Dubai Land Department open data. Progress figures change when DLD publishes a new inspection, so each row shows its inspection date.