photo: hmbhomes.aeUnder constructionBeverly Grande
DLD developer no. 1220 · H M B HOMES REAL ESTATE DEVELOPMENT
Deals checked 29 Oct 2026 · project details as of 17 Jul 2026
Location
This project on Google
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 27 Oct 2026 | Sales | Off-plan | Flat · 2 B/R | 91.24 | 982 | 1,835,000 | 20,112 | 1,868 |
| 8 Oct 2026 | Sales | Off-plan | Flat · Studio | 40.66 | 438 | 779,305 | 19,166 | 1,781 |
| 8 Oct 2026 | Sales | Off-plan | Flat · 1 B/R | 78.9 | 849 | 1,253,070 | 15,882 | 1,475 |
| 1 Aug 2026 | Sales | Off-plan | Flat · 2 B/R | 135.26 | 1,456 | 1,820,000 | 13,456 | 1,250 |
| 1 Aug 2026 | Sales | Off-plan | Flat · Studio | 39.85 | 429 | 800,000 | 20,075 | 1,865 |
| 1 Aug 2026 | Sales | Off-plan | Flat · 1 B/R | 63.24 | 681 | 1,230,000 | 19,450 | 1,807 |
| 1 Aug 2026 | Sales | Off-plan | Flat · Studio | 42.67 | 459 | 750,000 | 17,577 | 1,633 |
| 22 Jul 2026 | Sales | Off-plan | Flat · Studio | 38.44 | 414 | 800,000 | 20,812 | 1,933 |
| 20 Jul 2026 | Sales | Off-plan | Flat · 2 B/R | 91.26 | 982 | 1,550,000 | 16,984 | 1,578 |
| 3 Jul 2026 | Sales | Off-plan | Flat · Studio | 39.85 | 429 | 685,000 | 17,189 | 1,597 |
| 3 Jul 2026 | Sales | Off-plan | Flat · Studio | 39.26 | 423 | 849,000 | 21,625 | 2,009 |
| 3 Jul 2026 | Sales | Off-plan | Flat · 1 B/R | 84.89 | 914 | 1,249,500 | 14,719 | 1,367 |
| 22 Jun 2026 | Sales | Off-plan | Flat · Studio | 39.85 | 429 | 770,000 | 19,322 | 1,795 |
| 22 Jun 2026 | Sales | Off-plan | Flat · 1 B/R | 87.9 | 946 | 1,568,000 | 17,838 | 1,657 |
| 18 Jun 2026 | Sales | Off-plan | Flat · 1 B/R | 65.33 | 703 | 1,279,000 | 19,578 | 1,819 |
Beverly Grande: common questions
Is Beverly Grande delayed?
It is behind plan. Construction was 2.27% complete at the last DLD inspection on 29 September 2026, while its registered timeline (planned completion 31 December 2026) would expect about 82% by then.
When is the handover of Beverly Grande?
The planned completion date registered with Dubai Land Department is 31 December 2026. Handover usually follows completion; the developer confirms the exact date.
How much of Beverly Grande is built?
Construction was 2.27% complete at the last DLD inspection on 29 September 2026, as published by Dubai Land Department.
Where is Beverly Grande located?
Beverly Grande is in Motor City, Dubai.
Who is the developer of Beverly Grande?
Beverly Grande is developed by H M B HOMES REAL ESTATE DEVELOPMENT (DLD developer no. 1220). It is registered with Dubai Land Department as project no. 3767.
Does Beverly Grande have an escrow account?
Yes. Dubai Land Department open data lists escrow account 019500000788. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in Beverly Grande?
The most recent sale registered with Dubai Land Department was on 27 October 2026 for AED 1,835,000. Across the 103 recorded sales, the average was AED 1,602 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.