EVERGRIN HOUSE 2photo: object-1.comActive
Progress
10.29%
Handover
~ Dec 2026
Escrow
#19522911

EVERGRIN HOUSE 2

#4114 · OBJ1 REAL ESTATE DEVELOPMENT L.L.C · Al Satwa · 193 units

More from Object 1
declared value 35.0M AED data last checked 12 Sept 2026

 G + 2P + 8 Residential + R

Construction progress

10.29% of construction complete · last inspected by DLD 21 Jul 2026

≈55 pts behind the planned pace as of the last inspection

today
inspected 21 Jul 2026
start 15 Sept 2025 est. finish 30 Dec 2026