VIVID TOWERphoto: object-1.comActive
Progress
12.31%
Handover
~ Nov 2026
Escrow
#19390528

VIVID TOWER

#3380 · OBJ1 REAL ESTATE DEVELOPMENT L.L.C · Al Barsha South Fifth · 147 units

More from Object 1
declared value 38.0M AED data last checked 12 Sept 2026

UG Watertank+G+4P+16+R RESIDENTIAL BLDG. The project designed to have a concrete structure and block with internal and external finishes.

Construction progress

12.31% of construction complete · last inspected by DLD 12 Aug 2026

≈71 pts behind the planned pace as of the last inspection

today
inspected 12 Aug 2026
start 20 Jan 2025 est. finish 30 Nov 2026