photo: binghatti.comUnder constructionDLD developer no. 1051 · Binghatti Developers FZE
Data last checked 29 Oct 2026
More from Binghatti →3B+G+1M (Common) + 2 towers ( 25F+1MEC+R),(6F+R)
Location
This project on Google
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 22 Oct 2026 | Sales | Off-plan | Flat · 1 B/R | 75.31 | 811 | 2,000,000 | 26,557 | 2,467 |
| 20 Oct 2026 | Sales | Off-plan | Flat · Studio | 39.59 | 426 | 1,190,999 | 30,083 | 2,795 |
| 14 Oct 2026 | Sales | Off-plan | Flat · 1 B/R | 77.28 | 832 | 2,000,000 | 25,880 | 2,404 |
| 13 Oct 2026 | Sales | Off-plan | Flat · 1 B/R | 84.34 | 908 | 2,000,000 | 23,714 | 2,203 |
| 12 Oct 2026 | Sales | Off-plan | Flat · 1 B/R | 76.41 | 822 | 2,000,000 | 26,175 | 2,432 |
| 12 Oct 2026 | Sales | Off-plan | Flat · 1 B/R | 76.42 | 823 | 2,000,000 | 26,171 | 2,431 |
| 12 Oct 2026 | Sales | Off-plan | Flat · 1 B/R | 76.41 | 822 | 2,000,000 | 26,175 | 2,432 |
| 12 Oct 2026 | Sales | Off-plan | Flat · 1 B/R | 76.42 | 823 | 2,000,000 | 26,171 | 2,431 |
| 9 Oct 2026 | Sales | Off-plan | Flat · 1 B/R | 66.26 | 713 | 1,900,000 | 28,675 | 2,664 |
| 6 Oct 2026 | Sales | Off-plan | Flat · 1 B/R | 84.34 | 908 | 2,001,999 | 23,737 | 2,205 |
| 6 Oct 2026 | Sales | Off-plan | Flat · 1 B/R | 76.41 | 822 | 2,000,000 | 26,175 | 2,432 |
| 6 Oct 2026 | Sales | Off-plan | Flat · 2 B/R | 266.65 | 2,870 | 3,250,000 | 12,188 | 1,132 |
| 6 Oct 2026 | Sales | Off-plan | Flat · 2 B/R | 124.27 | 1,338 | 3,500,000 | 28,164 | 2,617 |
| 5 Oct 2026 | Sales | Off-plan | Flat · 1 B/R | 77.29 | 832 | 2,000,000 | 25,877 | 2,404 |
| 5 Oct 2026 | Sales | Off-plan | Flat · 1 B/R | 76.41 | 822 | 2,000,000 | 26,175 | 2,432 |
Binghatti Aquarise: common questions
Is Binghatti Aquarise delayed?
It is behind plan. Construction was 21.04% complete at the last DLD inspection on 14 May 2026, while its registered timeline (planned completion 31 October 2026) would expect about 71% by then.
When is the handover of Binghatti Aquarise?
The planned completion date registered with Dubai Land Department is 31 October 2026. Handover usually follows completion; the developer confirms the exact date.
How much of Binghatti Aquarise is built?
Construction was 21.04% complete at the last DLD inspection on 14 May 2026, as published by Dubai Land Department.
Where is Binghatti Aquarise located?
Binghatti Aquarise is in Business Bay, Dubai.
Who is the developer of Binghatti Aquarise?
Binghatti Aquarise is developed by Binghatti Developers FZE (DLD developer no. 1051). It is registered with Dubai Land Department as project no. 3585, with 1,602 units.
Does Binghatti Aquarise have an escrow account?
Yes. Dubai Land Department open data lists escrow account 9009226759924005. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in Binghatti Aquarise?
The most recent sale registered with Dubai Land Department was on 22 October 2026 for AED 2,000,000. Across the 225 recorded sales, the average was AED 2,641 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.