Luxury Family Residencephoto: kappaacca.aeActive
Progress
75.95%
Handover
Escrow
#0205799354002

Luxury Family Residence

#2353 · Kappa Acca Real Estate Development · Jumeirah Village Circle

data last checked 17 Jul 2026

Construction progress

75.95% of construction complete · last inspected by DLD 25 Apr 2026

overdue — planned finish was 31 Dec 2023, still at 75.95%

today
inspected 25 Apr 2026
start 15 Aug 2019 est. finish 31 Dec 2023