photo: h-h.aeUnder constructionBaccarat Hotel and Residences, Dubai
DLD developer no. 1580 · BC RESIDENCES L.L.C
Data last checked 29 Oct 2026
B2+G+44 and B2+G+27
Location
This project on Google
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 21 Sept 2026 | Sales | Off-plan | Flat · 3 B/R | 399.17 | 4,297 | 25,164,433.42 | 63,042 | 5,857 |
| 7 Jul 2026 | Sales | Off-plan | Flat · 3 B/R | 422.94 | 4,552 | 19,500,000 | 46,106 | 4,283 |
| 6 Jul 2026 | Sales | Off-plan | Flat · 3 B/R | 396.53 | 4,268 | 20,235,742.52 | 51,032 | 4,741 |
| 2 Jul 2026 | Sales | Off-plan | Flat · 3 B/R | 421.9 | 4,541 | 19,986,189 | 47,372 | 4,401 |
| 17 Jun 2026 | Sales | Off-plan | Flat · 5 B/R | 875.75 | 9,426 | 53,000,000 | 60,520 | 5,622 |
| 1 Jun 2026 | Sales | Off-plan | Flat · 4 B/R | 486.26 | 5,234 | 40,000,000 | 82,261 | 7,642 |
| 21 May 2026 | Sales | Off-plan | Flat · 3 B/R | 383.7 | 4,130 | 28,300,000 | 73,756 | 6,852 |
| 15 May 2026 | Sales | Off-plan | Flat · 4 B/R | 486.26 | 5,234 | 34,156,321 | 70,243 | 6,526 |
| 7 Apr 2026 | Sales | Off-plan | Flat · 4 B/R | 934.49 | 10,059 | 57,448,926.23 | 61,476 | 5,711 |
| 6 Apr 2026 | Sales | Off-plan | Flat · 4 B/R | 914.27 | 9,841 | 55,970,851.12 | 61,219 | 5,687 |
| 6 Apr 2026 | Sales | Off-plan | Flat · 3 B/R | 433.67 | 4,668 | 19,243,741.25 | 44,374 | 4,122 |
| 6 Apr 2026 | Sales | Off-plan | Flat · 3 B/R | 410.21 | 4,415 | 19,878,290.19 | 48,459 | 4,502 |
| 6 Apr 2026 | Sales | Off-plan | Flat · 3 B/R | 425.38 | 4,579 | 19,458,191.22 | 45,743 | 4,250 |
| 2 Apr 2026 | Sales | Off-plan | Flat · 3 B/R | 403.25 | 4,341 | 22,180,410 | 55,004 | 5,110 |
| 1 Apr 2026 | Sales | Off-plan | Flat · 4 B/R | 757.11 | 8,149 | 47,253,000 | 62,412 | 5,798 |
Baccarat Hotel and Residences, Dubai: common questions
Is Baccarat Hotel and Residences, Dubai delayed?
It is behind plan. Construction was 21.16% complete at the last DLD inspection on 3 September 2026, while its registered timeline (planned completion 29 December 2026) would expect about 92% by then.
When is the handover of Baccarat Hotel and Residences, Dubai?
The planned completion date registered with Dubai Land Department is 29 December 2026. Handover usually follows completion; the developer confirms the exact date.
How much of Baccarat Hotel and Residences, Dubai is built?
Construction was 21.16% complete at the last DLD inspection on 3 September 2026, as published by Dubai Land Department.
Where is Baccarat Hotel and Residences, Dubai located?
Baccarat Hotel and Residences, Dubai is in Burj Khalifa, Dubai.
Who is the developer of Baccarat Hotel and Residences, Dubai?
Baccarat Hotel and Residences, Dubai is developed by BC RESIDENCES L.L.C (DLD developer no. 1580). It is registered with Dubai Land Department as project no. 2724, with 99 units.
Does Baccarat Hotel and Residences, Dubai have an escrow account?
Yes. Dubai Land Department open data lists escrow account 0205834624402. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in Baccarat Hotel and Residences, Dubai?
The most recent sale registered with Dubai Land Department was on 21 September 2026 for AED 25,164,433. Across the 27 recorded sales, the average was AED 5,896 per sq ft.