Beachfront Gates 2
DLD developer no. 1142 · DUBAI SOUTH PROPERTIES DWC LLC
Data last checked 29 Oct 2026
The land use of the project is B+G+7+roof floors commercial & residential apartments.
Location
This project on Google
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 26 Oct 2026 | Mortgage | Off-plan | Flat · 2 B/R | 115.33 | 1,241 | 800,000 | 6,937 | 644 |
| 23 Oct 2026 | Sales | Off-plan | Flat · 2 B/R | 151.05 | 1,626 | 2,179,237 | 14,427 | 1,340 |
| 8 Oct 2026 | Sales | Off-plan | Flat · 2 B/R | 112.94 | 1,216 | 1,522,465 | 13,480 | 1,252 |
| 25 Sept 2026 | Sales | Off-plan | Flat · 2 B/R | 123.98 | 1,335 | 1,795,598 | 14,483 | 1,346 |
| 18 Sept 2026 | Sales | Off-plan | Flat · 3 B/R | 180.58 | 1,944 | 2,626,996 | 14,548 | 1,352 |
| 16 Sept 2026 | Sales | Off-plan | Flat · 2 B/R | 123.81 | 1,333 | 1,786,239 | 14,427 | 1,340 |
| 15 Sept 2026 | Sales | Off-plan | Flat · 2 B/R | 112.99 | 1,216 | 1,511,098 | 13,374 | 1,242 |
| 15 Sept 2026 | Sales | Off-plan | Flat · 3 B/R | 181.24 | 1,951 | 2,477,406 | 13,669 | 1,270 |
| 14 Sept 2026 | Sales | Off-plan | Flat · 2 B/R | 112.94 | 1,216 | 1,528,482 | 13,534 | 1,257 |
| 2 Sept 2026 | Mortgage | Off-plan | Flat · 1 B/R | 91.28 | 983 | 618,667 | 6,778 | 630 |
| 3 Aug 2026 | Sales | Off-plan | Flat · 2 B/R | 123.98 | 1,335 | 1,802,504 | 14,539 | 1,351 |
| 30 Jul 2026 | Sales | Off-plan | Flat · 3 B/R | 180.58 | 1,944 | 2,547,690 | 14,108 | 1,311 |
| 30 Jul 2026 | Sales | Off-plan | Flat · 2 B/R | 123.98 | 1,335 | 1,788,691 | 14,427 | 1,340 |
| 24 Jul 2026 | Sales | Off-plan | Flat · 1 B/R | 79.79 | 859 | 1,106,447 | 13,867 | 1,288 |
| 15 Jul 2026 | Sales | Off-plan | Flat · 1 B/R | 80.01 | 861 | 1,092,876 | 13,659 | 1,269 |
Beachfront Gates 2: common questions
Is Beachfront Gates 2 delayed?
It is behind plan. Construction was 41.73% complete at the last DLD inspection on 14 July 2026, while its registered timeline (planned completion 30 December 2026) would expect about 75% by then.
When is the handover of Beachfront Gates 2?
The planned completion date registered with Dubai Land Department is 30 December 2026. Handover usually follows completion; the developer confirms the exact date.
How much of Beachfront Gates 2 is built?
Construction was 41.73% complete at the last DLD inspection on 14 July 2026, as published by Dubai Land Department.
Where is Beachfront Gates 2 located?
Beachfront Gates 2 is in Madinat Al Mataar, Dubai.
Who is the developer of Beachfront Gates 2?
Beachfront Gates 2 is developed by DUBAI SOUTH PROPERTIES DWC LLC (DLD developer no. 1142). It is registered with Dubai Land Department as project no. 3379, with 162 units.
Does Beachfront Gates 2 have an escrow account?
Yes. Dubai Land Department open data lists escrow account 10613405920008. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in Beachfront Gates 2?
The most recent sale registered with Dubai Land Department was on 23 October 2026 for AED 2,179,237. Across the 19 recorded sales, the average was AED 1,306 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.