Active
Progress
50.8%
Handover
~ Oct 2026
Escrow
#0205803195811

AG CENTRAL

#2422 · AG PROPERTIES L.L.C · Wadi Al Safa 5 · 99 units

escrow #0205803195811 declared value 34.0M AED

Escrow bank is not published in DLD open data — verify the escrow agent via Dubai REST before paying into the account.

One Residential Building 1B + G + 11 + R,The project designed to have a concrete structure and block with internal and external finishes.

Construction progress

50.8% of construction complete · last inspected by DLD 26 Jan 2026

on pace — ≈24 pts behind the plan as of the last inspection

today
inspected 26 Jan 2026
start 31 Oct 2023 est. finish 31 Oct 2026