AURA PRESTIGEphoto: aurainfinite.aeActive
Progress
20.65%
Handover
~ Nov 2026
Escrow
#001582193587201

AURA PRESTIGE

#3788 · AURA INFINITE REAL ESTATE DEVELOPMENT L.L.C · Nadd Hessa · 81 units

declared value 38.0M AED data last checked 12 Sept 2026

Lower Ground + Ground + 8 Floor Retail and Residential Development

Construction progress

20.65% of construction complete · last inspected by DLD 30 Apr 2026

≈44 pts behind the planned pace as of the last inspection

today
inspected 30 Apr 2026
start 1 Jun 2025 est. finish 1 Nov 2026