Active
Progress
3.04%
Handover
~ Oct 2026
Escrow
#019000090000

Whitestone Residence

#3536 · AXIOM PRIME REAL ESTATE DEVELOPMENT L.L.C · Al Satwa · 46 units

declared value 31.3M AED data last checked 12 Sept 2026

G+2P+8+R

Construction progress

3.04% of construction complete · last inspected by DLD 6 Jul 2026

≈74 pts behind the planned pace as of the last inspection

today
inspected 6 Jul 2026
start 1 Jun 2025 est. finish 31 Oct 2026