Progress
95.07%
Handover
Escrow
#019500000394

California Village

#2694 · Gfh Real Estate L.L.C · Wadi Al Safa 4

data last checked 17 Jul 2026

Construction progress

95.07% of construction complete · last inspected by DLD 8 May 2026

overdue — planned finish was 15 Jul 2025, still at 95.07%

today
inspected 8 May 2026
start 15 Mar 2023 est. finish 15 Jul 2025