DAMAC LAGOONS - NICE 2photo: damacproperties.comActive
Progress
83.88%
Handover
Escrow
#0205789887412

DAMAC LAGOONS - NICE 2

#2336 · ISLAND OASIS PROPERTIES · Al Hebiah Fifth

More from Damac
data last checked 17 Jul 2026

Construction progress

83.88% of construction complete · last inspected by DLD 17 Aug 2026

overdue — planned finish was 29 Jul 2025, still at 83.88%

today
inspected 17 Aug 2026
start 28 Feb 2022 est. finish 29 Jul 2025
Google · this project
3.0
2 reviews