California 2 by SDphoto: samanadevelopers.comActive
Progress
14.61%
Handover
~ Oct 2026
Escrow
#1008898486

California 2 by SD

#2883 · SAMANA STAR REAL ESTATE DEVELOPMENT L.L.C · Jabal Ali First · 155 units

More from Samana
declared value 43.0M AED data last checked 12 Sept 2026

G+2P+10+R,The project designed to have a concrete structure and block with internal and external finishes.

Construction progress

14.61% of construction complete · last inspected by DLD 28 Apr 2026

≈65 pts behind the planned pace as of the last inspection

today
inspected 28 Apr 2026
start 30 Apr 2024 est. finish 31 Oct 2026
Google · this project
4.6