photo: dugasta.comUnder constructionAl Haseen Residence 4
DLD developer no. 1157 · DUGASTA PROPERTIES DEVELOPMENT L.L.C
Data last checked 29 Oct 2026
B+G+5+R
Location
This project on Google
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 12 Oct 2026 | Sales | Off-plan | Flat · Studio | 35.81 | 385 | 629,071 | 17,567 | 1,632 |
| 12 Oct 2026 | Sales | Off-plan | Flat · Studio | 35.81 | 385 | 629,071 | 17,567 | 1,632 |
| 12 Oct 2026 | Sales | Off-plan | Flat · Studio | 35.81 | 385 | 629,071 | 17,567 | 1,632 |
| 12 Oct 2026 | Sales | Off-plan | Flat · Studio | 35.44 | 381 | 648,499 | 18,299 | 1,700 |
| 12 Oct 2026 | Sales | Off-plan | Flat · Studio | 35.64 | 384 | 537,082 | 15,070 | 1,400 |
| 12 Oct 2026 | Sales | Off-plan | Flat · Studio | 35.38 | 381 | 533,162 | 15,070 | 1,400 |
| 9 Oct 2026 | Sales | Off-plan | Flat · Studio | 35.76 | 385 | 654,364 | 18,299 | 1,700 |
| 6 Oct 2026 | Sales | Off-plan | Flat · Studio | 35.21 | 379 | 530,600 | 15,070 | 1,400 |
| 6 Oct 2026 | Sales | Off-plan | Flat · Studio | 35.64 | 384 | 537,082 | 15,070 | 1,400 |
| 23 Sept 2026 | Sales | Off-plan | Flat · Studio | 35.21 | 379 | 606,400 | 17,222 | 1,600 |
| 23 Sept 2026 | Sales | Off-plan | Flat · Studio | 35.38 | 381 | 584,955 | 16,533 | 1,536 |
| 11 Sept 2026 | Sales | Off-plan | Flat · Studio | 35.89 | 386 | 579,480 | 16,146 | 1,500 |
| 11 Sept 2026 | Sales | Off-plan | Flat · Studio | 35.81 | 385 | 600,084 | 16,757 | 1,557 |
| 8 Sept 2026 | Sales | Off-plan | Flat · Studio | 35.44 | 381 | 460,434.02 | 12,992 | 1,207 |
| 8 Sept 2026 | Sales | Off-plan | Flat · Studio | 27.11 | 292 | 385,189 | 14,208 | 1,320 |
Al Haseen Residence 4: common questions
Is Al Haseen Residence 4 delayed?
It is behind plan. Construction was 11.76% complete at the last DLD inspection on 14 July 2026, while its registered timeline (planned completion 30 December 2026) would expect about 69% by then.
When is the handover of Al Haseen Residence 4?
The planned completion date registered with Dubai Land Department is 30 December 2026. Handover usually follows completion; the developer confirms the exact date.
How much of Al Haseen Residence 4 is built?
Construction was 11.76% complete at the last DLD inspection on 14 July 2026, as published by Dubai Land Department.
Where is Al Haseen Residence 4 located?
Al Haseen Residence 4 is in Dubai Industrial City, Dubai. Dubai Land Department records it under the Saih Shuaib 2 area.
Who is the developer of Al Haseen Residence 4?
Al Haseen Residence 4 is developed by DUGASTA PROPERTIES DEVELOPMENT L.L.C (DLD developer no. 1157). It is registered with Dubai Land Department as project no. 3562, with 248 units.
Does Al Haseen Residence 4 have an escrow account?
Yes. Dubai Land Department open data lists escrow account 0205771071202. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in Al Haseen Residence 4?
The most recent sale registered with Dubai Land Department was on 12 October 2026 for AED 629,071. Across the 89 recorded sales, the average was AED 1,445 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.