DAMAC LAGOONS - PORTOFINOphoto: damacproperties.comActive
Progress
97.14%
Handover
Escrow
#0205789887416

DAMAC LAGOONS - PORTOFINO

#2356 · ISLAND OASIS PROPERTIES · Al Hebiah Fifth

More from Damac
data last checked 17 Jul 2026

Construction progress

97.14% of construction complete · last inspected by DLD 16 Jul 2026

overdue — planned finish was 29 Jun 2025, still at 97.14%

today
inspected 16 Jul 2026
start 24 Apr 2022 est. finish 29 Jun 2025