Dubai projects with handover in 2028
360 projects registered with Dubai Land Department have a planned completion date in 2028. Of these, 201 are on track by their latest DLD inspection and 159 are behind plan or past their date. Updated daily from DLD open data.
All 360 projects
Sorted by the planned completion date registered with Dubai Land Department; progress is the latest DLD inspection.
| Project | Developer | DLD-inspected progress | Inspected | Planned completion | Status |
|---|---|---|---|---|---|
![]() | ANAX DEVELOPMENTS L.L.C | 7 Oct 2026 | 1 Jan 2028 | On track | |
![]() | JAIEDCO REAL ESTATE DEVELOPMENT L.L.C | 22 Jun 2026 | 1 Jan 2028 | On track | |
![]() | METEORA REAL ESTATE DEVELOPMENT L.L.C | 6 Feb 2025 | 1 Jan 2028 | On track | |
![]() | Regent Star Property Developments L.L.C | 10 Jun 2026 | 2 Jan 2028 | Behind plan | |
![]() | Harbour One Investment L.L.C | 11 Aug 2026 | 14 Jan 2028 | On track | |
![]() | Harbour One Investment L.L.C | 11 Aug 2026 | 14 Jan 2028 | On track | |
![]() | NSHAMA PROPERTIES OWNED BY NSHMI DEVELOPMENT ONE PERSON COMPANY L.L.C | 10 Sept 2026 | 14 Jan 2028 | Behind plan | |
![]() | AZIZI DEVELOPMENTS L.L.C | 25 Mar 2026 | 15 Jan 2028 | Behind plan | |
![]() | AZIZI DEVELOPMENTS L.L.C | 24 Mar 2026 | 16 Jan 2028 | Behind plan | |
![]() | THE PALM - JEBEL ALI CO. (L.L.C) | 28 Sept 2026 | 17 Jan 2028 | Behind plan | |
![]() | THE PALM - JEBEL ALI CO. (L.L.C) | 28 Sept 2026 | 17 Jan 2028 | Behind plan | |
![]() | THE PALM - JEBEL ALI CO. (L.L.C) | 28 Sept 2026 | 17 Jan 2028 | Behind plan | |
![]() | THE PALM - JEBEL ALI CO. (L.L.C) | 28 Sept 2026 | 17 Jan 2028 | Behind plan | |
![]() | THE PALM - JEBEL ALI CO. (L.L.C) | 28 Sept 2026 | 17 Jan 2028 | Behind plan | |
![]() | THE PALM - JEBEL ALI CO. (L.L.C) | 28 Sept 2026 | 17 Jan 2028 | Behind plan | |
![]() | Flora Isle Real Estate Development L.L.C | 15 Jul 2026 | 18 Jan 2028 | Behind plan | |
![]() | AZIZI DEVELOPMENTS L.L.C | 25 Mar 2026 | 23 Jan 2028 | Behind plan | |
![]() | Mbr Mansions Real Estate Development L.L.C | 14 Oct 2026 | 24 Jan 2028 | On track | |
| AJWAN RESIDENCESMadinat Al Mataar | ESK INVESTMENTS - SOLE PROPRIETORSHIP L.L.C - DUBAI BRANCH | 4 Aug 2026 | 27 Jan 2028 | On track | |
![]() | Zee Development L.L.C | 22 Apr 2025 | 30 Jan 2028 | On track | |
![]() | Tfg S C Development L.L.C | 12 Oct 2026 | 31 Jan 2028 | On track | |
![]() | Prestige The Parkway Real Estate Development L.L.C | 17 Aug 2026 | 31 Jan 2028 | Behind plan | |
![]() | Wadi Hills City Real Estate Development L.L.C | 14 Sept 2026 | 31 Jan 2028 | Behind plan | |
![]() | AZIZI DEVELOPMENTS L.L.C | 18 Mar 2026 | 12 Feb 2028 | Behind plan | |
![]() | AZIZI DEVELOPMENTS L.L.C | 24 Mar 2026 | 13 Feb 2028 | Behind plan | |
![]() | NANMA PROPERTIES L.L.C | 15 Oct 2026 | 15 Feb 2028 | On track | |
![]() | VIVA REAL ESTATE DEVELOPMENT L.L.C | 23 Jun 2026 | 15 Feb 2028 | On track | |
![]() | NAS ESTATES L.L.C | 12 Aug 2026 | 15 Feb 2028 | Behind plan | |
![]() | Neoterra Real Estate Development L.L.C | 7 May 2026 | 15 Feb 2028 | On track | |
![]() | IMTIAZ GHD REAL ESTATE DEVELOPMENT L.L.C | 17 Aug 2026 | 15 Feb 2028 | On track |
Where 2028 handovers are
Developers with the most 2028 handovers
- AZIZI DEVELOPMENTS L.L.C13
- EMAAR DEVELOPMENT P.J.S.C.13
- REPORTAGE PLUS A REAL ESTATE DEVELOPMENT L.L.C12
- THE PALM - JEBEL ALI CO. (L.L.C)12
- DAMAC ELITE INVESTMENT CO. L.L.C9
- SAMANA SIGNATURE REAL ESTATE DEVELOPMENTS L.L.C9
- ELLINGTON PROPERTIES DEVELOPMENT L.L.C7
- NSHAMA PROPERTIES OWNED BY NSHMI DEVELOPMENT ONE PERSON COMPANY L.L.C6
Handover in 2028: common questions
Which Dubai projects are due for handover in 2028?
360 projects registered with Dubai Land Department have a planned completion date in 2028: 201 are on track by their latest DLD inspection and 159 are behind plan or past their date. The table on this page lists each one with its planned date and latest DLD-inspected progress.
When are most 2028 handovers due?
By planned completion date: Q1 84, Q2 87, Q3 65, Q4 124. The busiest quarter is Q4. Most are in Palm Deira (31), JVC (27), Dubai Land Residence Complex (23).
Is the DLD planned completion date the handover date?
Not exactly. It is the completion date the developer registered with Dubai Land Department. Handover to buyers usually follows completion and the building completion certificate, and developers can apply to change the date, so confirm the current schedule with the developer.
How do you decide if a project is on track?
The DLD-inspected percentage is compared with the progress expected from the project's registered start and planned completion dates at the time of the inspection. More than 25 percentage points short counts as behind plan; still under construction after the planned date counts as overdue.
Answers are generated from Dubai Land Department open data shown on this page.