Flora Islephoto: flora-isle.comActive
Progress
7.19%
Handover
~ Jan 2028
Escrow
#3538489321802

Flora Isle

#3440 · Flora Isle Real Estate Development L.L.C · Palm Deira

data last checked 17 Jul 2026

Construction progress

7.19% of construction complete · last inspected by DLD 15 Jul 2026

≈44 pts behind the planned pace as of the last inspection

today
inspected 15 Jul 2026
start 18 Dec 2024 est. finish 18 Jan 2028
Google · this project
5.0
1 reviews