photo: prestigeone.aeUnder constructionDeveloper: Prestige The Parkway Real Estate Development L.L.C
Deals checked 29 Oct 2026 · project details as of 17 Jul 2026
More from Prestige One →Location
No Google rating available for this project yet.
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 26 Oct 2026 | Sales | Off-plan | Flat · 3 B/R | 161.39 | 1,737 | 3,724,800 | 23,079 | 2,144 |
| 26 Oct 2026 | Sales | Off-plan | Flat · 2 B/R | 120.89 | 1,301 | 2,262,439 | 18,715 | 1,739 |
| 20 Oct 2026 | Sales | Off-plan | Flat · 1 B/R | 78.66 | 847 | 1,788,389 | 22,736 | 2,112 |
| 14 Oct 2026 | Sales | Off-plan | Flat · 1 B/R | 85.19 | 917 | 1,850,000 | 21,716 | 2,017 |
| 8 Oct 2026 | Sales | Off-plan | Flat · 1 B/R | 67.76 | 729 | 1,490,000 | 21,989 | 2,043 |
| 30 Jul 2026 | Sales | Off-plan | Flat · 2 B/R | 120.9 | 1,301 | 2,555,500 | 21,137 | 1,964 |
| 30 Jul 2026 | Sales | Off-plan | Flat · 2 B/R | 120.89 | 1,301 | 2,406,850 | 19,909 | 1,850 |
| 17 Jul 2026 | Sales | Off-plan | Flat · 2 B/R | 120.9 | 1,301 | 2,556,800 | 21,148 | 1,965 |
| 1 Jun 2026 | Sales | Off-plan | Flat · 2 B/R | 120.9 | 1,301 | 2,555,500 | 21,137 | 1,964 |
| 14 May 2026 | Sales | Off-plan | Flat · 1 B/R | 68.94 | 742 | 1,313,453.25 | 19,052 | 1,770 |
| 11 May 2026 | Sales | Off-plan | Flat · 2 B/R | 120.87 | 1,301 | 2,798,450 | 23,153 | 2,151 |
| 23 Apr 2026 | Sales | Off-plan | Flat · 2 B/R | 103.51 | 1,114 | 2,142,000 | 20,694 | 1,923 |
| 13 Apr 2026 | Sales | Off-plan | Flat · 2 B/R | 120.7 | 1,299 | 2,915,000 | 24,151 | 2,244 |
| 12 Mar 2026 | Sales | Off-plan | Flat · 1 B/R | 85.04 | 915 | 1,768,481.2 | 20,796 | 1,932 |
| 12 Mar 2026 | Sales | Off-plan | Flat · 3 B/R | 161.39 | 1,737 | 3,356,251.08 | 20,796 | 1,932 |
PARKWAY BY PRESTIGE ONE: common questions
Is PARKWAY BY PRESTIGE ONE delayed?
It is behind plan. Construction was 10.89% complete at the last DLD inspection on 17 August 2026, while its registered timeline (planned completion 31 January 2028) would expect about 51% by then.
When is the handover of PARKWAY BY PRESTIGE ONE?
The planned completion date registered with Dubai Land Department is 31 January 2028. Handover usually follows completion; the developer confirms the exact date.
How much of PARKWAY BY PRESTIGE ONE is built?
Construction was 10.89% complete at the last DLD inspection on 17 August 2026, as published by Dubai Land Department.
Where is PARKWAY BY PRESTIGE ONE located?
PARKWAY BY PRESTIGE ONE is in Horizon, Dubai.
Who is the developer of PARKWAY BY PRESTIGE ONE?
PARKWAY BY PRESTIGE ONE is developed by Prestige The Parkway Real Estate Development L.L.C. It is registered with Dubai Land Department as project no. 3272.
Does PARKWAY BY PRESTIGE ONE have an escrow account?
Yes. Dubai Land Department open data lists escrow account 0405899885806. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in PARKWAY BY PRESTIGE ONE?
The most recent sale registered with Dubai Land Department was on 26 October 2026 for AED 3,724,800. Across the 37 recorded sales, the average was AED 2,016 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.