Palm Jebel Ali - Frond Dphoto: palmjebelali.aeActive
Progress
4.23%
Handover
~ Jan 2028
Escrow
#29176678

Palm Jebel Ali - Frond D

#3395 · THE PALM - JEBEL ALI CO. (L.L.C) · Palm Jabal Ali

data last checked 17 Jul 2026

Construction progress

4.23% of construction complete · last inspected by DLD 18 Jun 2026

≈43 pts behind the planned pace as of the last inspection

today
inspected 18 Jun 2026
start 14 Jan 2025 est. finish 17 Jan 2028