photo: karmadevelopers.aeUnder constructionTrinity By Karma
DLD developer no. 1645 · KARMA REALTY DEVELOPERS L.L.C
Data last checked 29 Oct 2026
G+P+15,The project designed to have a concrete structure and block with internal and external finishes.
Location
This project on Google
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 6 Oct 2026 | Gifts | Off-plan | Flat · 1 B/R | 67.9 | 731 | 1,125,006.26 | 16,569 | 1,539 |
| 11 Jun 2026 | Sales | Off-plan | Flat · 2 B/R | 159.15 | 1,713 | 1,892,803 | 11,893 | 1,105 |
| 11 Jun 2026 | Sales | Off-plan | Flat · 2 B/R | 117.37 | 1,263 | 1,783,488 | 15,195 | 1,412 |
| 11 Jun 2026 | Sales | Off-plan | Flat · 2 B/R | 186.59 | 2,008 | 2,218,700 | 11,891 | 1,105 |
| 1 Jun 2026 | Sales | Off-plan | Flat · 2 B/R | 158.44 | 1,705 | 2,051,446 | 12,948 | 1,203 |
| 27 Apr 2026 | Sales | Off-plan | Flat · 1 B/R | 69.81 | 751 | 1,112,535.27 | 15,937 | 1,481 |
| 22 Apr 2026 | Sales | Off-plan | Flat · 2 B/R | 161.22 | 1,735 | 2,000,017 | 12,406 | 1,153 |
| 20 Apr 2026 | Sales | Off-plan | Flat · 2 B/R | 99.35 | 1,069 | 1,716,860.25 | 17,281 | 1,605 |
| 2 Apr 2026 | Sales | Off-plan | Flat · 1 B/R | 72.03 | 775 | 1,082,285.7 | 15,025 | 1,396 |
| 2 Apr 2026 | Sales | Off-plan | Flat · 1 B/R | 70.76 | 762 | 1,037,106 | 14,657 | 1,362 |
| 9 Feb 2026 | Sales | Off-plan | Flat · 2 B/R | 168.85 | 1,817 | 2,105,719 | 12,471 | 1,159 |
| 22 Jan 2026 | Sales | Off-plan | Flat · 1 B/R | 75.18 | 809 | 1,103,805.14 | 14,682 | 1,364 |
| 22 Jan 2026 | Sales | Off-plan | Flat · 1 B/R | 72.41 | 779 | 1,086,444.96 | 15,004 | 1,394 |
| 22 Jan 2026 | Sales | Off-plan | Flat · 1 B/R | 79.85 | 859 | 1,176,832.43 | 14,738 | 1,369 |
Trinity By Karma: common questions
Is Trinity By Karma delayed?
It is behind plan. Construction was 30.87% complete at the last DLD inspection on 30 September 2026, while its registered timeline (planned completion 1 December 2026) would expect about 93% by then.
When is the handover of Trinity By Karma?
The planned completion date registered with Dubai Land Department is 1 December 2026. Handover usually follows completion; the developer confirms the exact date.
How much of Trinity By Karma is built?
Construction was 30.87% complete at the last DLD inspection on 30 September 2026, as published by Dubai Land Department.
Where is Trinity By Karma located?
Trinity By Karma is in Arjan, Dubai. Dubai Land Department records it under the Al Barshaa South Third area.
Who is the developer of Trinity By Karma?
Trinity By Karma is developed by KARMA REALTY DEVELOPERS L.L.C (DLD developer no. 1645). It is registered with Dubai Land Department as project no. 2933, with 309 units.
Does Trinity By Karma have an escrow account?
Yes. Dubai Land Department open data lists escrow account 1031225838233004. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in Trinity By Karma?
The most recent sale registered with Dubai Land Department was on 11 June 2026 for AED 1,892,803. Across the 13 recorded sales, the average was AED 1,316 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.