photo: gems-estate.comDelayed 25 mo.DLD developer no. 954 · DAMAC CRESCENT PROPERTIES
Deals checked 30 Oct 2026 · project details as of 17 Jul 2026
More from Damac →No Google rating available for this project yet.
Sale register covers the last ~3 months.
No sales match this filter in the stored window.
DAMAC HILLS - GEMS ESTATES 2: common questions
Is DAMAC HILLS - GEMS ESTATES 2 delayed?
Yes. Its planned completion date registered with Dubai Land Department was 15 September 2024, and at the last DLD inspection on 14 April 2026 construction was 62.64% complete.
When is the handover of DAMAC HILLS - GEMS ESTATES 2?
The planned completion date registered with Dubai Land Department is 15 September 2024. That date has passed and construction is still under way, so confirm the current schedule with the developer.
How much of DAMAC HILLS - GEMS ESTATES 2 is built?
Construction was 62.64% complete at the last DLD inspection on 14 April 2026, as published by Dubai Land Department.
Who is the developer of DAMAC HILLS - GEMS ESTATES 2?
DAMAC HILLS - GEMS ESTATES 2 is developed by DAMAC CRESCENT PROPERTIES (DLD developer no. 954). It is registered with Dubai Land Department as project no. 2457.
Does DAMAC HILLS - GEMS ESTATES 2 have an escrow account?
Yes. Dubai Land Department open data lists escrow account 465511920030. Always confirm the account with the developer or in the Dubai REST app before paying.
Answers are generated from Dubai Land Department open data shown on this page.