Dubai project escrow accounts
2,831 Dubai projects have an escrow account number in Dubai Land Department's registry, 1,478 of them under construction. Dubai Law No. 8 of 2007 requires off-plan developers to take buyers' payments into the project's own escrow account. Confirm the number with the developer or in the Dubai REST app before you pay.
| Project | Developer | Escrow account | Status | Planned completion |
|---|---|---|---|---|
| 08 Life ResidencesInternational City Ph 2 & 3 (Warsan Fourth) | DENIZ PROPERTIES L.L.C | 0205899161703 | Delayed 5 mo.64.87% | 31 May 2026 |
| 09 Life ResidencesDubai Land Residence Complex (Wadi Al Safa 5) | DENIZ PROPERTIES L.L.C | 1011226903887002 | Under construction6.84% | 1 Dec 2027 |
| 10 OXFORD by IMANJumeirah Village Circle | IMAN DEVELOPERS L.L.C | 0205302400816 | Under construction91.25% | — |
| 105 Residences by KamdarJumeirah Village Circle | Kamdar Property Development L.L.C | 019500000687 | Under construction12.45% | 28 Feb 2027 |
| 11 Hills ParkDubai Science Park | TOWNX REAL ESTATE DEVELOPMENT L.L.C | 1009725373 | Under construction80.05% | 31 Mar 2027 |
| 113 ResidencesSufouh Gardens (Al Safouh First) | IMAN DEVELOPERS L.L.C | 019500000947 | Off-plan0% | 28 Feb 2029 |
| 15 CascadeMotor City | IMAN DEVELOPERS L.L.C | 0205302400822 | Under construction5.5% | 30 Sept 2028 |
| 161 Jumeirah LaneAl Satwa | NATIONAL PROPERTIES OWNED BY NATIONAL BONDS CORPORATION SOLE PROPRIETORSHIP PSC SOLE PROPRIETORSHIP L.L.C | 001582112104401 | Delayed 8 mo.70.04% | 1 Mar 2026 |
| 171 Garden HeightsAl Satwa | JAD GLOBAL REAL ESTATE DEVELOPMENT L.L.C | 001582116499101 | Under construction33.66% | 31 Dec 2026 |
| 18 Marlow RowAl Barsha South Fourth | SAI AVANI REAL ESTATE DEVELOPERS L.L.C | 201044643 | Under construction51.92% | 31 Dec 2026 |
| 1WOOD ResidenceJumeirah Village Circle | OBJECT ONE REAL ESTATE DEVELOPMENT L.L.C | 19210878 | Under construction93.67% | — |
| 1WOOD Residence 2JVC (Al Barsha South Fourth) | OBJECT ONE REAL ESTATE DEVELOPMENT L.L.C | 29539630 | Off-plan0% | 20 Oct 2027 |
| 241 WatersidePalm Deira | LEGACY STAR REAL ESTATE DEVELOPMENT L.L.C | 0205935550405 | Under construction0.02% | 15 Jun 2028 |
| 24HCUm Hurair Second | O&F DHCC REAL ESTATE DEVELOPMENT L.L.C | 3001750226000 | Under construction80% | 30 Mar 2027 |
| 27 East End Garden Residences By Mirha Homes Real Estate DevelopmentInternational City Ph 2 & 3 | Mirha Homes Real Estate Development L.L.C | 019500000745 | Under construction40.26% | 31 Jan 2027 |
| 31 Above By BeyondMadinat Dubai Almelaheyah | BEYOND VESPERA REAL ESTATE DEVELOPMENT L.L.C | 0205937400402 | Under construction0.51% | 30 Dec 2028 |
| 311 Boulevard by Bam EskanJumeirah Village Circle | Bam Eskan Real Estate Development L.L.C | 13766416920002 | Under construction10% | 1 Oct 2027 |
| 368 Park LnJVC (Al Barsha South Fourth) | TABEER REAL ESTATE DEVELOPMENT L.L.C | 1011226170006005 | Off-plan0% | 31 Aug 2028 |
| 7 Park Central by MeteoraJumeirah Village Circle | METEORA REAL ESTATE DEVELOPMENT L.L.C | 12672051920005 | Delayed 18 mo.90.18% | 30 Apr 2025 |
| 77 Boulevard By BamAl Barsha South Fourth | BAM REAL ESTATE DEVELOPMENT L.L.C | 200828268 | Delayed 2 mo.18% | 10 Sept 2026 |
| 77SBusiness Bay | 77 SHADES OF GREEN REALESTATE DEVELOPMENT L.L.C | 0012226710002 | Under construction13.74% | 31 Dec 2028 |
| 99 Park PlaceJumeirah Village Circle | TABEER REAL ESTATE DEVELOPMENT L.L.C | 3538470978504 | Delayed 10 mo.90% | 31 Dec 2025 |
| 997 Residences by Reef Luxury DevelopmentPalm Deira | REEF LUXURY DEVELOPMENT L.L.C | 1011226141046010 | Under construction4.89% | 30 Mar 2028 |
| 999 Residences by Reef Luxury DevelopmentAl Furjan | REEF LUXURY DEVELOPMENT L.L.C | 1091226141046007 | Under construction13.21% | 30 Jun 2027 |
| A 99Dubai Land Residence Complex (Wadi Al Safa 5) | ARABIAN GULF PROPERTIES | 201025178 | Delayed47.83% | 31 Oct 2026 |
| Aark Terraces | AARK DEVELOPERS L.L.C | 019500000784 | Off-plan0% | 30 Jun 2028 |
| Aba Lux LivingDubai Marina | A B A Real Estate Development L.L.C | 0012053111003 | Under construction6.87% | — |
| Address Residences l Dubai Creek HarbourAl Khairan First | DUBAI CREEK HARBOUR L.L.C | 0205668118507 | Under construction26.44% | 31 Jan 2029 |
| Address Residences ZabeelZaabeel First | Zabeel Square L.L.C | 001582384837301 | Under construction14.7% | — |
| Address The BayDubai Harbour (Marsa Dubai) | EMAAR DEVELOPMENT P.J.S.C. | 1005129786 | Under construction70.08% | 31 Dec 2026 |
| AeonDubai Creek Harbour | DUBAI CREEK HARBOUR L.L.C | 0205668118502 | Under construction90.04% | — |
| Aero 1Dubai South | Bithaus Real Estate Development L.L.C | 1011226788783002 | Under construction35.57% | 15 Jul 2027 |
| Aeternitas TowerDubai Marina | LONDON GATE REAL ESTATE DEVELOPMENT L.L.C | 29373093 | Under construction57.85% | 11 Dec 2027 |
| Ag 7EVENDubai Land Residence Complex | AG PROPERTIES L.L.C | 0205803195808 | Under construction93.66% | 31 Mar 2027 |
| Ag 9INEDubai Land Residence Complex | AG PROPERTIES L.L.C | 0205803195813 | Under construction38.42% | — |
| Ag Ark TowerDubai Land Residence Complex | Agp Ark Real Estate Development L.L.C | 0205901997202 | Under construction14.06% | 30 Nov 2028 |
| Ag Aum ResidenceDubai Land Residence Complex | Agp Assets Real Estate Developments L.L.C | 0205899059402 | Under construction8.08% | 30 Nov 2028 |
| Ag CentralDubai Land Residence Complex (Wadi Al Safa 5) | AG PROPERTIES L.L.C | 0205803195811 | Delayed58.65% | 31 Oct 2026 |
| Ag SquareDubai Land Residence Complex (Wadi Al Safa 5) | AG PROPERTIES L.L.C | 0205803195805 | Delayed 1 mo.68.8% | 30 Sept 2026 |
| Agua Residences by Citi Developers - Tower 1Palm Deira | CITI DEVELOPERS REAL ESTATE DEVELOPMENT L.L.C | 012530689881 | Under construction5% | 31 Dec 2027 |
| Agua Residences by Citi Developers - Tower 2Palm Deira | CITI DEVELOPERS REAL ESTATE DEVELOPMENT L.L.C | 012300455067 | Under construction3.11% | 31 Dec 2027 |
| Ahs TowerTrade Center Second | Ahs Tower Holding Development L.L.C S.O.C | 14382075920002 | Under construction67.43% | 31 Jan 2027 |
| Ajwan ResidencesMadinat Al Mataar | ESK INVESTMENTS - SOLE PROPRIETORSHIP L.L.C - DUBAI BRANCH | 0012533679002 | Under construction10.02% | 27 Jan 2028 |
| Akala Hotels and ResidencesZaabeel Second | ARADA DEVELOPMENTS L.L.C S.O.C | 1009913193 | Under construction1.88% | 31 Oct 2029 |
| Al Ghaf JanoubMadinat Al Mataar | JERSEY REAL ESTATE DEVELOPMENT L.L.C | 0012111718005 | Off-plan0% | 15 Nov 2028 |
| Al Habtoor TowerBusiness Bay | AL HABTOOR CITY REAL ESTATE DEVELOPMENT (BR. OF DUBAI NATIONAL INVESTMENT CO L.L.C) | 001582335094301 | Under construction90.01% | 31 Dec 2026 |
| Al Haseen Residence 3Dubai Industrial City | DUGASTA PROPERTIES DEVELOPMENT L.L.C | 11879528920006 | Under construction10.08% | 15 May 2027 |
| Al Haseen Residence 4Dubai Industrial City (Saih Shuaib 2) | DUGASTA PROPERTIES DEVELOPMENT L.L.C | 0205771071202 | Under construction11.76% | 30 Dec 2026 |
| Al Haseen Residence 5Saih Shuaib 2 | DUGASTA PROPERTIES DEVELOPMENT L.L.C | 11879528920008 | Under construction4.22% | 3 Jun 2027 |
| Al VistaHorizon | DUBAI INVESTMENT REAL ESTATE (L L C) | 019000091147 | Under construction9.51% | 20 Oct 2027 |
Escrow accounts in Dubai: common questions
How do I verify a Dubai escrow account?
Find the project on this page or open its project page, and compare the escrow account number from Dubai Land Department's open data with the one in your sale and purchase agreement and payment request. Confirm it in the Dubai REST app or with the developer before you transfer money.
Why does an off-plan project need an escrow account?
Dubai Law No. 8 of 2007 on real estate development escrow accounts requires developers to pay buyers' money into an escrow account for that project at an approved bank. The money can only be released for construction of that project.
What if I am asked to pay into a different account?
Don't pay until you have checked. If the account does not match the project's escrow account, ask the developer for a written explanation and check the project with Dubai Land Department (for example in the Dubai REST app). This site is informational, not legal advice.
Where do the account numbers on this list come from?
Dubai Land Department's open project registry, refreshed daily. DLD does not publish the escrow bank, so a bank is shown only where it has been entered by hand from a public source.