11 Hills Parkphoto: townx.comUnder construction

11 Hills Park

DLD project no. 3324 · Dubai Science Park

Progress
80.05%
DLD inspected 30 Apr 2026
Handover
~ Mar 2027
Est. finish 31 Mar 2027
Escrow
#1009725373
Registered escrow account
Google rating
4.9 ★
8 reviews

DLD developer no. 1213 · TOWNX REAL ESTATE DEVELOPMENT L.L.C

Deals checked 29 Oct 2026 · project details as of 17 Jul 2026

DLDConstruction inspection
80.05% of construction complete · last inspected by DLD 30 Apr 2026

on pace with the planned timeline

today
inspected 30 Apr 2026
start 1 Nov 2024 est. finish 31 Mar 2027
Google · this project
4.9
8 reviews

Location

11 Hills Park: common questions

Is 11 Hills Park delayed?

Not by DLD figures. Construction was 80.05% complete at the last DLD inspection on 30 April 2026, in line with or ahead of its registered timeline (about 62% expected by then, planned completion 31 March 2027).

When is the handover of 11 Hills Park?

The planned completion date registered with Dubai Land Department is 31 March 2027. Handover usually follows completion; the developer confirms the exact date.

How much of 11 Hills Park is built?

Construction was 80.05% complete at the last DLD inspection on 30 April 2026, as published by Dubai Land Department.

Where is 11 Hills Park located?

11 Hills Park is in Dubai Science Park, Dubai.

Who is the developer of 11 Hills Park?

11 Hills Park is developed by TOWNX REAL ESTATE DEVELOPMENT L.L.C (DLD developer no. 1213). It is registered with Dubai Land Department as project no. 3324.

Does 11 Hills Park have an escrow account?

Yes. Dubai Land Department open data lists escrow account 1009725373. Always confirm the account with the developer or in the Dubai REST app before paying.

What are recent sale prices in 11 Hills Park?

The most recent sale registered with Dubai Land Department was on 9 October 2026 for AED 685,001. Across the 44 recorded sales, the average was AED 1,635 per sq ft.