Aeternitas Towerphoto: aeternitas-tower.comActive
Progress
48.72%
Handover
~ Dec 2027
Escrow
#29373093

Aeternitas Tower

#2797 · LONDON GATE REAL ESTATE DEVELOPMENT L.L.C · Dubai Marina

data last checked 17 Jul 2026

Construction progress

48.72% of construction complete · last inspected by DLD 12 Mar 2026

on pace — ≈8 pts behind the plan as of the last inspection

today
inspected 12 Mar 2026
start 1 Dec 2023 est. finish 11 Dec 2027