photo: reefdevelopments.aeUnder construction997 Residences by Reef Luxury Development
DLD developer no. 1944 · REEF LUXURY DEVELOPMENT L.L.C
Deals checked 29 Oct 2026 · project details as of 17 Jul 2026
Location
This project on Google
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 21 Sept 2026 | Sales | Off-plan | Flat · 1 B/R | 77.52 | 834 | 2,280,164.89 | 29,414 | 2,733 |
| 25 Jun 2026 | Sales | Off-plan | Flat · 2 B/R | 113.56 | 1,222 | 2,885,317.09 | 25,408 | 2,360 |
| 22 Jun 2026 | Sales | Off-plan | Flat · 2 B/R | 113.56 | 1,222 | 2,950,155.68 | 25,979 | 2,414 |
| 16 Jun 2026 | Sales | Off-plan | Flat · 1 B/R | 72.29 | 778 | 1,878,339.53 | 25,983 | 2,414 |
| 3 Jun 2026 | Sales | Off-plan | Flat · 1 B/R | 77.51 | 834 | 2,257,363.24 | 29,124 | 2,706 |
| 18 May 2026 | Sales | Off-plan | Flat · 1 B/R | 77.51 | 834 | 2,109,896.25 | 27,221 | 2,529 |
| 18 May 2026 | Sales | Off-plan | Flat · 1 B/R | 71.64 | 771 | 2,189,700.2 | 30,565 | 2,840 |
| 15 May 2026 | Sales | Off-plan | Flat · 1 B/R | 72.29 | 778 | 2,031,669.63 | 28,104 | 2,611 |
| 7 May 2026 | Sales | Off-plan | Flat · 1 B/R | 77.51 | 834 | 2,167,285.44 | 27,961 | 2,598 |
| 4 May 2026 | Sales | Off-plan | Flat · 2 B/R | 112.93 | 1,216 | 2,927,585.84 | 25,924 | 2,408 |
| 25 Mar 2026 | Sales | Off-plan | Flat · 1 B/R | 71.64 | 771 | 2,026,186.5 | 28,283 | 2,628 |
| 24 Mar 2026 | Sales | Off-plan | Flat · 1 B/R | 72.29 | 778 | 2,184,591 | 30,220 | 2,808 |
| 14 Feb 2026 | Sales | Off-plan | Flat · 1 B/R | 72.29 | 778 | 2,041,673.4 | 28,243 | 2,624 |
| 12 Feb 2026 | Sales | Off-plan | Flat · 1 B/R | 77.51 | 834 | 2,109,896.25 | 27,221 | 2,529 |
| 5 Jan 2026 | Sales | Off-plan | Flat · 1 B/R | 71.64 | 771 | 2,026,186.5 | 28,283 | 2,628 |
997 Residences by Reef Luxury Development: common questions
Is 997 Residences by Reef Luxury Development delayed?
It is behind plan. Construction was 4.89% complete at the last DLD inspection on 27 August 2026, while its registered timeline (planned completion 30 March 2028) would expect about 41% by then.
When is the handover of 997 Residences by Reef Luxury Development?
The planned completion date registered with Dubai Land Department is 30 March 2028. Handover usually follows completion; the developer confirms the exact date.
How much of 997 Residences by Reef Luxury Development is built?
Construction was 4.89% complete at the last DLD inspection on 27 August 2026, as published by Dubai Land Department.
Where is 997 Residences by Reef Luxury Development located?
997 Residences by Reef Luxury Development is in Palm Deira, Dubai.
Who is the developer of 997 Residences by Reef Luxury Development?
997 Residences by Reef Luxury Development is developed by REEF LUXURY DEVELOPMENT L.L.C (DLD developer no. 1944). It is registered with Dubai Land Department as project no. 3837.
Does 997 Residences by Reef Luxury Development have an escrow account?
Yes. Dubai Land Department open data lists escrow account 1011226141046010. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in 997 Residences by Reef Luxury Development?
The most recent sale registered with Dubai Land Department was on 21 September 2026 for AED 2,280,165. Across the 15 recorded sales, the average was AED 2,588 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.