Al Habtoor Towerphoto: thehabtoortower.comActive
Progress
90.01%
Handover
~ Dec 2026
Escrow
#001582335094301

Al Habtoor Tower

#2656 · AL HABTOOR CITY REAL ESTATE DEVELOPMENT (BR. OF DUBAI NATIONAL INVESTMENT CO L.L.C) · Business Bay · 6717 units

declared value 2.4B AED data last checked 12 Sept 2026

High Rise Residential Building 82 floors on Sh. Zayed Road(As per BP:- 3B+G+7P+77F, Residential/commercial).The project designed to have a concrete structure and block with internal and external finishes.

Construction progress

90.01% of construction complete · last inspected by DLD 31 Aug 2026

on pace — ≈2 pts behind the plan as of the last inspection

today
inspected 31 Aug 2026
start 1 Oct 2022 est. finish 31 Dec 2026