99 PARK PLACEphoto: tabeer.aeActive
Progress
80.6%
Handover
Escrow
#3538470978504

99 PARK PLACE

#2968 · TABEER REAL ESTATE DEVELOPMENT L.L.C · Jumeirah Village Circle

escrow #3538470978504

Escrow bank is not published in DLD open data — verify the escrow agent via Dubai REST before paying into the account.

No further description published for this project.

Construction progress

80.6% of construction complete · last inspected by DLD 8 Jun 2026

overdue — planned finish was 31 Dec 2025, still at 80.6%

today
inspected 8 Jun 2026
start 20 Feb 2024 est. finish 31 Dec 2025