More from AG Properties →One Residential Building (3B + G + P + 17 + R).The project designed to have a concrete structure and block with internal and external finishes.
Location
This project on Google
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 21 Oct 2026 | Sales | Off-plan | Flat · 1 B/R | 89.07 | 959 | 747,809 | 8,396 | 780 |
| 14 Jul 2026 | Sales | Off-plan | Flat · 1 B/R | 77.24 | 831 | 720,000 | 9,322 | 866 |
| 13 Jul 2026 | Sales | Off-plan | Flat · Studio | 40.92 | 440 | 500,000 | 12,219 | 1,135 |
| 10 Jun 2026 | Sales | Off-plan | Flat · 1 B/R | 86.06 | 926 | 754,983 | 8,773 | 815 |
| 5 Jun 2026 | Sales | Off-plan | Flat · Studio | 42.55 | 458 | 420,000 | 9,871 | 917 |
| 18 May 2026 | Sales | Off-plan | Flat · 1 B/R | 77.24 | 831 | 690,000 | 8,933 | 830 |
| 16 May 2026 | Sales | Off-plan | Flat · Studio | 47.86 | 515 | 468,832 | 9,796 | 910 |
| 16 May 2026 | Sales | Off-plan | Flat · 1 B/R | 89.07 | 959 | 750,000 | 8,420 | 782 |
| 11 May 2026 | Sales | Off-plan | Flat · Studio | 42.55 | 458 | 450,000 | 10,576 | 983 |
| 6 May 2026 | Sales | Off-plan | Flat · Studio | 49.36 | 531 | 531,250 | 10,763 | 1,000 |
| 12 Apr 2026 | Sales | Off-plan | Flat · Studio | 47.86 | 515 | 465,000 | 9,716 | 903 |
| 26 Mar 2026 | Sales | Off-plan | Flat · Studio | 42.92 | 462 | 408,861 | 9,526 | 885 |
| 10 Mar 2026 | Sales | Off-plan | Flat · 1 B/R | 136.46 | 1,469 | 732,569 | 5,368 | 499 |
| 5 Mar 2026 | Sales | Off-plan | Flat · 1 B/R | 69.15 | 744 | 635,000 | 9,183 | 853 |
| 25 Feb 2026 | Sales | Off-plan | Flat · Studio | 47.95 | 516 | 550,000 | 11,470 | 1,066 |
AG SQUARE: common questions
Is AG SQUARE delayed?
It is behind plan. Construction was 68.8% complete at the last DLD inspection on 10 September 2026, while its registered timeline (planned completion 30 September 2026) would expect about 99% by then.
When is the handover of AG SQUARE?
The planned completion date registered with Dubai Land Department is 30 September 2026. Handover usually follows completion; the developer confirms the exact date.
How much of AG SQUARE is built?
Construction was 68.8% complete at the last DLD inspection on 10 September 2026, as published by Dubai Land Department.
Where is AG SQUARE located?
AG SQUARE is in Dubai Land Residence Complex, Dubai. Dubai Land Department records it under the Wadi Al Safa 5 area.
Who is the developer of AG SQUARE?
AG SQUARE is developed by AG PROPERTIES L.L.C (DLD developer no. 1398). It is registered with Dubai Land Department as project no. 2424, with 372 units.
Does AG SQUARE have an escrow account?
Yes. Dubai Land Department open data lists escrow account 0205803195805. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in AG SQUARE?
The most recent sale registered with Dubai Land Department was on 21 October 2026 for AED 747,809. Across the 26 recorded sales, the average was AED 927 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.