Off-plan

Shione

DLD project no. 4501 · Palm Deira · 1310 units

Progress
0%
DLD inspected 2 Nov 2026
Handover
~ Dec 2030
Est. finish 31 Dec 2030
Escrow
#019000095751
Registered escrow account
Google rating
—

DLD developer no. 2477 · LUNAI REAL ESTATE DEVELOPMENT L.L.C

Data last checked 10 Nov 2026

declared value 575.0M AED

1 Basement +G+21/20

DLDConstruction inspection
0%of construction complete · last inspected by DLD 2 Nov 2026

on pace with the planned timeline

today
inspected 2 Nov 2026
start 31 Mar 2027est. finish 31 Dec 2030
Google · this project
0 reviews

Shione: common questions

Is Shione delayed?

Not by DLD figures. Construction was 0% complete at the last DLD inspection on 2 November 2026, in line with or ahead of its registered timeline (about 0% expected by then, planned completion 31 December 2030).

When is the handover of Shione?

The planned completion date registered with Dubai Land Department is 31 December 2030. Handover usually follows completion; the developer confirms the exact date.

How much of Shione is built?

Construction was 0% complete at the last DLD inspection on 2 November 2026, as published by Dubai Land Department.

Where is Shione located?

Shione is in Palm Deira, Dubai.

Who is the developer of Shione?

Shione is developed by LUNAI REAL ESTATE DEVELOPMENT L.L.C (DLD developer no. 2477). It is registered with Dubai Land Department as project no. 4501, with 1,310 units.

Does Shione have an escrow account?

Yes. Dubai Land Department open data lists escrow account 019000095751. Always confirm the account with the developer or in the Dubai REST app before paying.