Cancelled
Progress
1.6%
Handover
Escrow
#0379498724090

PARK VILLA'S 5

#1610 · ARABIAN GULF PROPERTIES ·

More from AG Properties
data last checked 17 Jul 2026

Construction progress

1.6% of construction complete · last inspected by DLD 17 May 2016

≈72 pts behind the planned pace as of the last inspection

last DLD inspection was 10.3 years ago — this figure may no longer reflect the site's actual progress

today inspected 17 May 2016
start 1 May 2015 est. finish 1 Oct 2016
Google · this project
0 reviews