Wellington Ocean Walkphoto: wellingtondevelopments.aeActive
Progress
15.9%
Handover
~ Dec 2028
Escrow
#200965242

Wellington Ocean Walk

#4026 · Wellington Ocean Real Estate Development L.L.C · Palm Deira

data last checked 17 Jul 2026

Construction progress

15.9% of construction complete · last inspected by DLD 27 Jul 2026

on pace — ≈11 pts behind the plan as of the last inspection

today
inspected 27 Jul 2026
start 16 Sept 2025 est. finish 16 Dec 2028