Wedyanphoto: alghuraircollection.comOff-plan

Wedyan

DLD project no. 4071 · Business Bay · 164 units

Progress
0%
DLD inspected 26 Aug 2026
Handover
~ Sept 2029
Est. finish 15 Sept 2029
Escrow
#019000089390
Registered escrow account
Google rating
4.0 ★
4 reviews

DLD developer no. 2054 · WEDYAN AL GHURAIR REAL ESTATE DEVELOPMENT L.L.C

Data last checked 29 Oct 2026

declared value 920.0M AED

Residential and Commercial Building (3B + G + 46 Floors + R)

DLDConstruction inspection
0% of construction complete · last inspected by DLD 26 Aug 2026

on pace — ≈13 pts behind the plan as of the last inspection

today
inspected 26 Aug 2026
start 15 Mar 2026 est. finish 15 Sept 2029
Google · this project
4.0
4 reviews

Location

Wedyan: common questions

Is Wedyan delayed?

Not by DLD figures. Construction was 0% complete at the last DLD inspection on 26 August 2026, in line with or ahead of its registered timeline (about 13% expected by then, planned completion 15 September 2029).

When is the handover of Wedyan?

The planned completion date registered with Dubai Land Department is 15 September 2029. Handover usually follows completion; the developer confirms the exact date.

How much of Wedyan is built?

Construction was 0% complete at the last DLD inspection on 26 August 2026, as published by Dubai Land Department.

Where is Wedyan located?

Wedyan is in Business Bay, Dubai.

Who is the developer of Wedyan?

Wedyan is developed by WEDYAN AL GHURAIR REAL ESTATE DEVELOPMENT L.L.C (DLD developer no. 2054). It is registered with Dubai Land Department as project no. 4071, with 164 units.

Does Wedyan have an escrow account?

Yes. Dubai Land Department open data lists escrow account 019000089390. Always confirm the account with the developer or in the Dubai REST app before paying.

Answers are generated from Dubai Land Department open data shown on this page.