photo: btproperties.aeUnder constructionWaada- Raiha
DLD developer no. 2254 · BT PROPERTIES DWC LLC
Deals checked 29 Oct 2026 · project details as of 17 Jul 2026
This project on Google
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 15 Oct 2026 | Sales | Off-plan | Villa · 4 B/R | 317.93 | 3,422 | 4,517,000 | 14,208 | 1,320 |
| 15 Oct 2026 | Sales | Off-plan | Villa · 4 B/R | 317.93 | 3,422 | 4,517,000 | 14,208 | 1,320 |
| 15 Oct 2026 | Sales | Off-plan | Villa · 4 B/R | 317.93 | 3,422 | 4,517,000 | 14,208 | 1,320 |
| 15 Oct 2026 | Sales | Off-plan | Villa · 4 B/R | 317.93 | 3,422 | 4,517,000 | 14,208 | 1,320 |
| 10 Aug 2026 | Sales | Off-plan | Villa · 4 B/R | 317.93 | 3,422 | 4,705,000 | 14,799 | 1,375 |
| 13 Jul 2026 | Sales | Off-plan | Villa · 4 B/R | 319.72 | 3,441 | 3,978,000 | 12,442 | 1,156 |
| 13 Jul 2026 | Sales | Ready | Airport | 423.93 | 4,563 | 5,803,000 | 13,689 | 1,272 |
| 13 Jul 2026 | Sales | Ready | Airport | 423.93 | 4,563 | 6,386,000 | 15,064 | 1,399 |
| 10 Jul 2026 | Sales | Ready | Airport | 423.93 | 4,563 | 5,821,000 | 13,731 | 1,276 |
| 10 Jul 2026 | Sales | Ready | Airport | 423.93 | 4,563 | 5,803,000 | 13,689 | 1,272 |
| 10 Jul 2026 | Sales | Off-plan | Villa · 4 B/R | 317.93 | 3,422 | 4,805,000 | 15,113 | 1,404 |
| 10 Jul 2026 | Sales | Off-plan | Villa · 4 B/R | 311.57 | 3,354 | 4,271,000 | 13,708 | 1,274 |
| 10 Jul 2026 | Sales | Off-plan | Villa · 4 B/R | 317.93 | 3,422 | 4,098,000 | 12,890 | 1,197 |
| 4 Jun 2026 | Sales | Ready | Airport | 423.93 | 4,563 | 5,821,000 | 13,731 | 1,276 |
| 13 May 2026 | Sales | Off-plan | Villa · 4 B/R | 317.93 | 3,422 | 4,098,000 | 12,890 | 1,197 |
Waada- Raiha: common questions
Is Waada- Raiha delayed?
It is behind plan. Construction was 7.04% complete at the last DLD inspection on 20 October 2026, while its registered timeline (planned completion 31 October 2028) would expect about 32% by then.
When is the handover of Waada- Raiha?
The planned completion date registered with Dubai Land Department is 31 October 2028. Handover usually follows completion; the developer confirms the exact date.
How much of Waada- Raiha is built?
Construction was 7.04% complete at the last DLD inspection on 20 October 2026, as published by Dubai Land Department.
Where is Waada- Raiha located?
Waada- Raiha is in Madinat Al Mataar, Dubai.
Who is the developer of Waada- Raiha?
Waada- Raiha is developed by BT PROPERTIES DWC LLC (DLD developer no. 2254). It is registered with Dubai Land Department as project no. 3783.
Does Waada- Raiha have an escrow account?
Yes. Dubai Land Department open data lists escrow account 3538494929002. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in Waada- Raiha?
The most recent sale registered with Dubai Land Department was on 15 October 2026 for AED 4,517,000. Across the 28 recorded sales, the average was AED 1,298 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.