Active
Progress
65.1%
Handover
Escrow
#19600185

W1

#4130 · MALINA W1 REAL ESTATE DEVELOPMENT L.L.C · Jabal Ali First · 83 units

escrow #19600185 declared value 52.0M AED

Escrow bank is not published in DLD open data — verify the escrow agent via Dubai REST before paying into the account.

Construction of G+2P+1ST+12TH+R Residential Building on plot no. AFMU020B

Construction progress

65.1% of construction complete · last inspected by DLD 4 Jun 2026

overdue — planned finish was 30 Apr 2026, still at 65.1%

today
inspected 4 Jun 2026
start 14 Mar 2024 est. finish 30 Apr 2026