photo: crystalbayintl.comDelayedVue by Crystal Bay
DLD developer no. 1909 · CRYSTAL BAY DEVELOPMENT L.L.C
Data last checked 29 Oct 2026
G+4P+17+R.The project designed to have a concrete structure and block with internal and external finishes.
Location
This project on Google
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 29 Sept 2026 | Sales | Off-plan | Flat · Studio | 39.18 | 422 | 622,000 | 15,875 | 1,475 |
| 27 Aug 2026 | Sales | Off-plan | Shop · NA | 68.33 | 735 | 2,100,000 | 30,733 | 2,855 |
| 22 Aug 2026 | Sales | Off-plan | Flat · Studio | 40.16 | 432 | 584,321.85 | 14,550 | 1,352 |
| 8 Aug 2026 | Sales | Off-plan | Flat · Studio | 36.87 | 397 | 800,000 | 21,698 | 2,016 |
| 5 Jun 2026 | Sales | Off-plan | Flat · 1 B/R | 80.11 | 862 | 1,189,974 | 14,854 | 1,380 |
| 5 Jun 2026 | Sales | Off-plan | Flat · 2 B/R | 118.75 | 1,278 | 1,680,595.48 | 14,152 | 1,315 |
| 20 May 2026 | Sales | Off-plan | Flat · 2 B/R | 118.75 | 1,278 | 1,728,809.43 | 14,558 | 1,353 |
| 20 May 2026 | Sales | Off-plan | Flat · 2 B/R | 156.06 | 1,680 | 2,212,770.28 | 14,179 | 1,317 |
| 3 May 2026 | Sales | Off-plan | Flat · Studio | 42 | 452 | 621,931.5 | 14,808 | 1,376 |
| 14 Apr 2026 | Sales | Off-plan | Flat · Studio | 37.3 | 401 | 750,000 | 20,107 | 1,868 |
| 14 Apr 2026 | Sales | Off-plan | Flat · Studio | 36.63 | 394 | 790,000 | 21,567 | 2,004 |
| 14 Apr 2026 | Sales | Off-plan | Flat · Studio | 37.55 | 404 | 542,179.76 | 14,439 | 1,341 |
| 15 Feb 2026 | Sales | Off-plan | Flat · 2 B/R | 117.86 | 1,269 | 1,650,000 | 14,000 | 1,301 |
| 5 Feb 2026 | Sales | Off-plan | Flat · 2 B/R | 118.83 | 1,279 | 1,575,000 | 13,254 | 1,231 |
| 5 Feb 2026 | Sales | Off-plan | Flat · Studio | 39.18 | 422 | 775,000 | 19,781 | 1,838 |
Vue by Crystal Bay: common questions
Is Vue by Crystal Bay delayed?
It is behind plan. Construction was 68.21% complete at the last DLD inspection on 27 August 2026, while its registered timeline (planned completion 1 October 2026) would expect about 96% by then.
When is the handover of Vue by Crystal Bay?
The planned completion date registered with Dubai Land Department is 1 October 2026. Handover usually follows completion; the developer confirms the exact date.
How much of Vue by Crystal Bay is built?
Construction was 68.21% complete at the last DLD inspection on 27 August 2026, as published by Dubai Land Department.
Where is Vue by Crystal Bay located?
Vue by Crystal Bay is in Jumeirah Village Circle (JVC), Dubai. Dubai Land Department records it under the Al Barsha South Fourth area.
Who is the developer of Vue by Crystal Bay?
Vue by Crystal Bay is developed by CRYSTAL BAY DEVELOPMENT L.L.C (DLD developer no. 1909). It is registered with Dubai Land Department as project no. 3090, with 176 units.
Does Vue by Crystal Bay have an escrow account?
Yes. Dubai Land Department open data lists escrow account 019000082982. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in Vue by Crystal Bay?
The most recent sale registered with Dubai Land Department was on 29 September 2026 for AED 622,000. Across the 20 recorded sales, the average was AED 1,535 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.