VOLTA TOWERphoto: damacproperties.comUnder construction

VOLTA TOWER

DLD project no. 2782 · Burj Khalifa

Progress
29.26%
DLD inspected 18 Aug 2026
Handover
~ Dec 2027
Est. finish 31 Dec 2027
Escrow
#0205860533902
Registered escrow account
Google rating
4.5 ★
19 reviews

Developer: Damac C S L Investment L.L.C

Deals checked 29 Oct 2026 · project details as of 17 Jul 2026

More from Damac →
DLDConstruction inspection
29.26% of construction complete · last inspected by DLD 18 Aug 2026

≈37 pts behind the planned pace as of the last inspection

today
inspected 18 Aug 2026
start 13 Dec 2023 est. finish 31 Dec 2027
Google · this project
4.5
19 reviews

Location

VOLTA TOWER: common questions

Is VOLTA TOWER delayed?

It is behind plan. Construction was 29.26% complete at the last DLD inspection on 18 August 2026, while its registered timeline (planned completion 31 December 2027) would expect about 66% by then.

When is the handover of VOLTA TOWER?

The planned completion date registered with Dubai Land Department is 31 December 2027. Handover usually follows completion; the developer confirms the exact date.

How much of VOLTA TOWER is built?

Construction was 29.26% complete at the last DLD inspection on 18 August 2026, as published by Dubai Land Department.

Where is VOLTA TOWER located?

VOLTA TOWER is in Burj Khalifa, Dubai.

Who is the developer of VOLTA TOWER?

VOLTA TOWER is developed by Damac C S L Investment L.L.C. It is registered with Dubai Land Department as project no. 2782.

Does VOLTA TOWER have an escrow account?

Yes. Dubai Land Department open data lists escrow account 0205860533902. Always confirm the account with the developer or in the Dubai REST app before paying.

What are recent sale prices in VOLTA TOWER?

The most recent sale registered with Dubai Land Department was on 27 July 2026 for AED 2,301,120. Across the 17 recorded sales, the average was AED 2,351 per sq ft.

Answers are generated from Dubai Land Department open data shown on this page.