Active
Progress
1.49%
Handover
~ Aug 2028
Escrow
#1031006177206007

VIBE

#4083 · ARSENAL EAST REAL ESTATE DEVELOPMENT L.L.C · Al Satwa · 212 units

declared value 59.4M AED data last checked 12 Sept 2026

Building 1 (Building A): 8F+R, Building 2 (Building B): 8F+R Shared (Ground + Podium): G+2P

Construction progress

1.49% of construction complete · last inspected by DLD 9 Apr 2026

on pace — ≈15 pts behind the plan as of the last inspection

today
inspected 9 Apr 2026
start 15 Oct 2025 est. finish 31 Aug 2028