photo: visiondevelopments.aeUnder constructionVERDE BY VISION
DLD developer no. 1806 · CLEAR VISION REAL ESTATE DEVELOPMENT L.L.C
Deals checked 29 Oct 2026 · project details as of 17 Jul 2026
No Google rating available for this project yet.
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 16 Oct 2026 | Sales | Off-plan | Flat · 2 B/R | 115.45 | 1,243 | 1,655,370 | 14,338 | 1,332 |
| 16 Oct 2026 | Sales | Off-plan | Flat · 2 B/R | 115.46 | 1,243 | 1,727,190 | 14,959 | 1,390 |
| 16 Oct 2026 | Sales | Off-plan | Flat · 1 B/R | 78.59 | 846 | 1,088,652.6 | 13,852 | 1,287 |
| 14 Oct 2026 | Sales | Off-plan | Flat · 2 B/R | 117.51 | 1,265 | 1,731,690 | 14,737 | 1,369 |
| 14 Oct 2026 | Sales | Off-plan | Flat · Studio | 40.68 | 438 | 689,940 | 16,960 | 1,576 |
| 29 Sept 2026 | Sales | Off-plan | Flat · Studio | 41.91 | 451 | 677,520 | 16,166 | 1,502 |
| 21 Sept 2026 | Sales | Off-plan | Flat · 1 B/R | 72.67 | 782 | 1,297,222.22 | 17,851 | 1,658 |
| 10 Sept 2026 | Sales | Off-plan | Flat · 3 B/R | 146.04 | 1,572 | 2,186,782 | 14,974 | 1,391 |
| 8 Sept 2026 | Sales | Off-plan | Flat · 1 B/R | 78.83 | 849 | 1,167,570 | 14,811 | 1,376 |
| 8 Sept 2026 | Sales | Off-plan | Flat · 1 B/R | 78.59 | 846 | 1,128,870 | 14,364 | 1,334 |
| 25 Aug 2026 | Sales | Off-plan | Flat · Studio | 40.68 | 438 | 658,800 | 16,195 | 1,505 |
| 25 Aug 2026 | Sales | Off-plan | Flat · 1 B/R | 64.54 | 695 | 1,025,493 | 15,889 | 1,476 |
| 25 Aug 2026 | Sales | Off-plan | Flat · 1 B/R | 72.67 | 782 | 1,057,860 | 14,557 | 1,352 |
| 24 Aug 2026 | Sales | Off-plan | Flat · 1 B/R | 78.83 | 849 | 1,135,398.6 | 14,403 | 1,338 |
| 24 Aug 2026 | Sales | Off-plan | Flat · 3 B/R | 146.04 | 1,572 | 2,146,500 | 14,698 | 1,365 |
VERDE BY VISION: common questions
Is VERDE BY VISION delayed?
It is behind plan. Construction was 11.97% complete at the last DLD inspection on 12 October 2026, while its registered timeline (planned completion 30 September 2027) would expect about 45% by then.
When is the handover of VERDE BY VISION?
The planned completion date registered with Dubai Land Department is 30 September 2027. Handover usually follows completion; the developer confirms the exact date.
How much of VERDE BY VISION is built?
Construction was 11.97% complete at the last DLD inspection on 12 October 2026, as published by Dubai Land Department.
Where is VERDE BY VISION located?
VERDE BY VISION is in Dubai Sports City, Dubai.
Who is the developer of VERDE BY VISION?
VERDE BY VISION is developed by CLEAR VISION REAL ESTATE DEVELOPMENT L.L.C (DLD developer no. 1806). It is registered with Dubai Land Department as project no. 4124.
Does VERDE BY VISION have an escrow account?
Yes. Dubai Land Department open data lists escrow account 012025657819. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in VERDE BY VISION?
The most recent sale registered with Dubai Land Department was on 16 October 2026 for AED 1,655,370. Across the 217 recorded sales, the average was AED 1,410 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.