Verdana Residence 4photo: reportagegroup.comActive
Progress
0.04%
Handover
~ Sept 2028
Escrow
#1009725290

Verdana Residence 4

#3340 · REPORTAGE PLUS A REAL ESTATE DEVELOPMENT L.L.C · Dubai Investment Park First · 784 units

declared value 138.4M AED data last checked 12 Sept 2026

 Residential Building 1B+2P+G+15+R - 392 unit

Construction progress

0.04% of construction complete · last inspected by DLD 5 Aug 2026

≈28 pts behind the planned pace as of the last inspection

today
inspected 5 Aug 2026
start 30 Sept 2025 est. finish 30 Sept 2028
Google · this project
5.0