Veona by Guttiphoto: gutti.aeActive
Progress
11.08%
Handover
~ Dec 2027
Escrow
#019500000817

Veona by Gutti

#4001 · Gutti Real Estate Development L.L.C · Dubai Land Residence Complex

data last checked 17 Jul 2026

Construction progress

11.08% of construction complete · last inspected by DLD 18 Jun 2026

on pace — ≈18 pts behind the plan as of the last inspection

today
inspected 18 Jun 2026
start 1 Nov 2025 est. finish 31 Dec 2027
Google · this project