photo: acubedevelopments.comUnder constructionVEGA
Developer: Acube Real Estate Development L L C
Deals checked 29 Oct 2026 · project details as of 17 Jul 2026
No Google rating available for this project yet.
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 23 Oct 2026 | Sales | Off-plan | Flat · 1 B/R | 69.29 | 746 | 1,193,229.45 | 17,221 | 1,600 |
| 16 Oct 2026 | Sales | Off-plan | Flat · 2 B/R | 99.69 | 1,073 | 1,596,654.36 | 16,016 | 1,488 |
| 16 Oct 2026 | Sales | Off-plan | Flat · 2 B/R | 99.68 | 1,073 | 1,627,089.08 | 16,323 | 1,516 |
| 16 Oct 2026 | Sales | Off-plan | Flat · 1 B/R | 69.29 | 746 | 1,199,088.76 | 17,305 | 1,608 |
| 8 Oct 2026 | Sales | Off-plan | Flat · Studio | 45.16 | 486 | 867,802.09 | 19,216 | 1,785 |
| 6 Oct 2026 | Sales | Off-plan | Flat · 2 B/R | 99.69 | 1,073 | 1,562,167.5 | 15,670 | 1,456 |
| 20 May 2026 | Sales | Off-plan | Flat · 2 B/R | 99.68 | 1,073 | 1,613,182.94 | 16,184 | 1,504 |
| 19 May 2026 | Sales | Off-plan | Flat · Studio | 38.3 | 412 | 347,403 | 9,071 | 843 |
| 14 Apr 2026 | Sales | Off-plan | Flat · 2 B/R | 100.07 | 1,077 | 1,602,741.11 | 16,016 | 1,488 |
| 14 Apr 2026 | Sales | Off-plan | Flat · 2 B/R | 100.07 | 1,077 | 1,518,386.31 | 15,173 | 1,410 |
| 28 Mar 2026 | Sales | Off-plan | Flat · 2 B/R | 99.68 | 1,073 | 1,629,870.11 | 16,351 | 1,519 |
| 28 Mar 2026 | Sales | Off-plan | Flat · 1 B/R | 69.29 | 746 | 1,206,900.19 | 17,418 | 1,618 |
| 26 Jan 2026 | Sales | Off-plan | Flat · 1 B/R | 69.29 | 746 | 1,230,910.38 | 17,765 | 1,650 |
| 15 Jan 2026 | Sales | Off-plan | Flat · 2 B/R | 99.56 | 1,072 | 1,477,071.35 | 14,836 | 1,378 |
| 7 Jan 2026 | Sales | Off-plan | Flat · 2 B/R | 99.69 | 1,073 | 1,653,793 | 16,589 | 1,541 |
VEGA: common questions
Is VEGA delayed?
It is behind plan. Construction was 20.3% complete at the last DLD inspection on 19 August 2026, while its registered timeline (planned completion 15 May 2027) would expect about 68% by then.
When is the handover of VEGA?
The planned completion date registered with Dubai Land Department is 15 May 2027. Handover usually follows completion; the developer confirms the exact date.
How much of VEGA is built?
Construction was 20.3% complete at the last DLD inspection on 19 August 2026, as published by Dubai Land Department.
Where is VEGA located?
VEGA is in Dubai Sports City, Dubai.
Who is the developer of VEGA?
VEGA is developed by Acube Real Estate Development L L C. It is registered with Dubai Land Department as project no. 3414.
Does VEGA have an escrow account?
Yes. Dubai Land Department open data lists escrow account 001582260960401. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in VEGA?
The most recent sale registered with Dubai Land Department was on 23 October 2026 for AED 1,193,229. Across the 15 recorded sales, the average was AED 1,494 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.