photo: tomorrowworldgroup.aeUnder constructionTomorrow 166
DLD developer no. 1977 · TOMORROW WORLD REAL ESTATE DEVELOPMENT L.L.C
Deals checked 29 Oct 2026 · project details as of 17 Jul 2026
Location
This project on Google
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 21 Oct 2026 | Sales | Off-plan | Flat · 2 B/R | 148.86 | 1,602 | 3,290,000 | 22,101 | 2,053 |
| 15 Oct 2026 | Sales | Off-plan | Flat · 2 B/R | 149.87 | 1,613 | 3,420,000 | 22,820 | 2,120 |
| 2 Sept 2026 | Gifts | Off-plan | Flat · 2 B/R | 149.87 | 1,613 | 3,242,511.9 | 21,635 | 2,010 |
| 31 Aug 2026 | Gifts | Off-plan | Flat · 2 B/R | 149.87 | 1,613 | 3,242,511.9 | 21,635 | 2,010 |
| 13 Aug 2026 | Sales | Off-plan | Flat · 1 B/R | 139.26 | 1,499 | 2,891,000 | 20,760 | 1,929 |
| 7 Jul 2026 | Sales | Off-plan | Flat · 2 B/R | 145.68 | 1,568 | 3,230,000 | 22,172 | 2,060 |
| 6 May 2026 | Sales | Off-plan | Flat · 2 B/R | 148.86 | 1,602 | 3,260,000 | 21,900 | 2,035 |
| 5 May 2026 | Sales | Off-plan | Flat · 2 B/R | 229.76 | 2,473 | 3,880,000 | 16,887 | 1,569 |
| 22 Apr 2026 | Sales | Off-plan | Flat · 2 B/R | 149.87 | 1,613 | 3,255,000 | 21,719 | 2,018 |
| 22 Apr 2026 | Sales | Off-plan | Flat · 2 B/R | 146.69 | 1,579 | 3,199,200 | 21,809 | 2,026 |
| 22 Apr 2026 | Sales | Off-plan | Flat · 2 B/R | 149.87 | 1,613 | 3,199,200 | 21,347 | 1,983 |
| 22 Apr 2026 | Sales | Off-plan | Flat · 2 B/R | 146.69 | 1,579 | 3,380,000 | 23,042 | 2,141 |
| 22 Apr 2026 | Sales | Off-plan | Flat · 2 B/R | 148.86 | 1,602 | 3,230,000 | 21,698 | 2,016 |
| 22 Apr 2026 | Sales | Off-plan | Flat · 1 B/R | 104.01 | 1,120 | 2,650,000 | 25,478 | 2,367 |
| 7 Apr 2026 | Sales | Off-plan | Flat · 3 B/R | 225.95 | 2,432 | 4,000,000 | 17,703 | 1,645 |
Tomorrow 166: common questions
Is Tomorrow 166 delayed?
It is behind plan. Construction was 1.68% complete at the last DLD inspection on 1 April 2026, while its registered timeline (planned completion 31 May 2027) would expect about 42% by then.
When is the handover of Tomorrow 166?
The planned completion date registered with Dubai Land Department is 31 May 2027. Handover usually follows completion; the developer confirms the exact date.
How much of Tomorrow 166 is built?
Construction was 1.68% complete at the last DLD inspection on 1 April 2026, as published by Dubai Land Department.
Where is Tomorrow 166 located?
Tomorrow 166 is in Palm Deira, Dubai.
Who is the developer of Tomorrow 166?
Tomorrow 166 is developed by TOMORROW WORLD REAL ESTATE DEVELOPMENT L.L.C (DLD developer no. 1977). It is registered with Dubai Land Department as project no. 3638.
Does Tomorrow 166 have an escrow account?
Yes. Dubai Land Department open data lists escrow account 19427206. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in Tomorrow 166?
The most recent sale registered with Dubai Land Department was on 21 October 2026 for AED 3,290,000. Across the 29 recorded sales, the average was AED 2,118 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.