photo: tmepropertyuae.comDelayed 4 mo.Time 2
DLD developer no. 527 · TIME PROPERTIES
Data last checked 29 Oct 2026
1 Basement+Ground+3 Podiums+16 Typical/Residential Floors.The project designed to have a concrete structure and block with internal and external finishes.
Location
This project on Google
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 10 Oct 2026 | Sales | Off-plan | Flat · 1 B/R | 69.94 | 753 | 765,000 | 10,938 | 1,016 |
| 5 Oct 2026 | Sales | Off-plan | Flat · Studio | 30.65 | 330 | 490,000 | 15,987 | 1,485 |
| 5 Oct 2026 | Sales | Off-plan | Flat · 2 B/R | 106.64 | 1,148 | 1,070,000 | 10,034 | 932 |
| 2 Oct 2026 | Sales | Off-plan | Flat · 1 B/R | 71.89 | 774 | 780,000 | 10,850 | 1,008 |
| 18 Sept 2026 | Sales | Off-plan | Flat · 1 B/R | 70.02 | 754 | 725,000 | 10,354 | 962 |
| 8 Sept 2026 | Sales | Off-plan | Flat · 1 B/R | 69.74 | 751 | 730,000 | 10,467 | 972 |
| 1 Sept 2026 | Sales | Off-plan | Flat · 1 B/R | 73.88 | 795 | 760,000 | 10,287 | 956 |
| 25 Aug 2026 | Sales | Off-plan | Flat · 1 B/R | 71.22 | 767 | 725,000 | 10,180 | 946 |
| 21 Aug 2026 | Sales | Off-plan | Flat · 1 B/R | 70.52 | 759 | 720,000 | 10,210 | 949 |
| 29 Jul 2026 | Sales | Off-plan | Flat · 1 B/R | 71 | 764 | 790,000 | 11,127 | 1,034 |
| 24 Jul 2026 | Sales | Off-plan | Flat · 2 B/R | 96.85 | 1,042 | 925,000 | 9,551 | 887 |
| 18 Jul 2026 | Sales | Off-plan | Flat · 1 B/R | 69.94 | 753 | 735,000 | 10,509 | 976 |
| 15 Jul 2026 | Sales | Off-plan | Flat · 1 B/R | 71.22 | 767 | 765,000 | 10,741 | 998 |
| 13 Jul 2026 | Sales | Off-plan | Flat · 1 B/R | 69.55 | 749 | 785,000 | 11,287 | 1,049 |
| 16 Jun 2026 | Sales | Off-plan | Flat · 1 B/R | 71.88 | 774 | 770,000 | 10,712 | 995 |
Time 2: common questions
Is Time 2 delayed?
Not by DLD figures. Construction was 87.1% complete at the last DLD inspection on 28 April 2026, in line with or ahead of its registered timeline (about 97% expected by then, planned completion 1 June 2026).
When is the handover of Time 2?
The planned completion date registered with Dubai Land Department is 1 June 2026. Handover usually follows completion; the developer confirms the exact date.
How much of Time 2 is built?
Construction was 87.1% complete at the last DLD inspection on 28 April 2026, as published by Dubai Land Department.
Where is Time 2 located?
Time 2 is in Dubai Land Residence Complex, Dubai. Dubai Land Department records it under the Wadi Al Safa 5 area.
Who is the developer of Time 2?
Time 2 is developed by TIME PROPERTIES (DLD developer no. 527). It is registered with Dubai Land Department as project no. 2541, with 304 units.
Does Time 2 have an escrow account?
Yes. Dubai Land Department open data lists escrow account 3717244832614. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in Time 2?
The most recent sale registered with Dubai Land Department was on 10 October 2026 for AED 765,000. Across the 26 recorded sales, the average was AED 1,009 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.