photo: sccvertex.comUnder constructionThe Willows Residences
Developer: Scc Vertex Property L.L.C
Deals checked 29 Oct 2026 · project details as of 17 Jul 2026
Location
This project on Google
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 4 Sept 2026 | Sales | Off-plan | Flat · 2 B/R | 90.96 | 979 | 1,762,970 | 19,382 | 1,801 |
| 24 Jul 2026 | Sales | Off-plan | Flat · 1 B/R | 65.42 | 704 | 1,216,000 | 18,588 | 1,727 |
| 25 Jun 2026 | Sales | Off-plan | Flat · 2 B/R | 90.88 | 978 | 1,800,000 | 19,806 | 1,840 |
| 24 Jun 2026 | Sales | Off-plan | Flat · 2 B/R | 84.5 | 910 | 1,700,000 | 20,118 | 1,869 |
| 24 Jun 2026 | Sales | Off-plan | Flat · 2 B/R | 84.56 | 910 | 1,684,551 | 19,921 | 1,851 |
| 20 May 2026 | Sales | Off-plan | Flat · 2 B/R | 90.96 | 979 | 2,000,888 | 21,997 | 2,044 |
| 10 Apr 2026 | Sales | Off-plan | Flat · 1 B/R | 65.42 | 704 | 1,344,076 | 20,545 | 1,909 |
| 7 Apr 2026 | Sales | Off-plan | Flat · 2 B/R | 90.8 | 977 | 1,862,365 | 20,511 | 1,906 |
| 6 Apr 2026 | Sales | Off-plan | Flat · 1 B/R | 63.78 | 687 | 1,304,388 | 20,451 | 1,900 |
| 6 Apr 2026 | Sales | Off-plan | Flat · 2 B/R | 84.62 | 911 | 1,785,250 | 21,097 | 1,960 |
| 14 Mar 2026 | Sales | Off-plan | Flat · 2 B/R | 90.88 | 978 | 1,833,779 | 20,178 | 1,875 |
| 13 Mar 2026 | Sales | Off-plan | Flat · 1 B/R | 63.78 | 687 | 1,308,168 | 20,511 | 1,906 |
| 26 Feb 2026 | Sales | Off-plan | Flat · 1 B/R | 75.26 | 810 | 1,543,630 | 20,511 | 1,906 |
| 25 Feb 2026 | Sales | Off-plan | Flat · 2 B/R | 84.7 | 912 | 1,718,469 | 20,289 | 1,885 |
| 25 Feb 2026 | Sales | Off-plan | Flat · 1 B/R | 64.92 | 699 | 1,397,580 | 21,528 | 2,000 |
The Willows Residences: common questions
Is The Willows Residences delayed?
It is behind plan. Construction was 0.74% complete at the last DLD inspection on 14 April 2026, while its registered timeline (planned completion 30 June 2027) would expect about 31% by then.
When is the handover of The Willows Residences?
The planned completion date registered with Dubai Land Department is 30 June 2027. Handover usually follows completion; the developer confirms the exact date.
How much of The Willows Residences is built?
Construction was 0.74% complete at the last DLD inspection on 14 April 2026, as published by Dubai Land Department.
Where is The Willows Residences located?
The Willows Residences is in Wadi Al Safa 3, Dubai.
Who is the developer of The Willows Residences?
The Willows Residences is developed by Scc Vertex Property L.L.C. It is registered with Dubai Land Department as project no. 3571.
Does The Willows Residences have an escrow account?
Yes. Dubai Land Department open data lists escrow account 012019069387. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in The Willows Residences?
The most recent sale registered with Dubai Land Department was on 4 September 2026 for AED 1,762,970. Across the 16 recorded sales, the average was AED 1,889 per sq ft.