photo: ellingtonproperties.aeUnder constructionDLD developer no. 1117 · ELLINGTON PROPERTIES DEVELOPMENT L.L.C
Deals checked 29 Oct 2026 · project details as of 17 Jul 2026
More from Ellington →Location
This project on Google
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 13 Jul 2026 | Sales | Off-plan | Villa · 3 B/R | 185.93 | 2,001 | 7,277,828 | 39,143 | 3,636 |
| 8 Jul 2026 | Sales | Off-plan | Villa · 4 B/R | 376.96 | 4,058 | 12,499,828 | 33,160 | 3,081 |
| 3 Jul 2026 | Sales | Off-plan | Villa · 3 B/R | 185.93 | 2,001 | 6,804,828 | 36,599 | 3,400 |
| 2 Jul 2026 | Sales | Off-plan | Villa · 3 B/R | 255.17 | 2,747 | 7,529,828 | 29,509 | 2,741 |
| 8 May 2026 | Sales | Off-plan | Villa · 3 B/R | 195.83 | 2,108 | 6,431,828 | 32,844 | 3,051 |
| 8 May 2026 | Sales | Off-plan | Villa · 4 B/R | 377 | 4,058 | 11,017,828 | 29,225 | 2,715 |
| 4 May 2026 | Sales | Off-plan | Villa · 4 B/R | 377 | 4,058 | 9,874,828 | 26,193 | 2,433 |
| 27 Apr 2026 | Sales | Off-plan | Villa · 4 B/R | 377 | 4,058 | 10,899,828 | 28,912 | 2,686 |
| 20 Apr 2026 | Sales | Off-plan | Villa · 3 B/R | 205.52 | 2,212 | 6,543,828 | 31,840 | 2,958 |
| 20 Apr 2026 | Sales | Off-plan | Villa · 3 B/R | 243.49 | 2,621 | 7,690,828 | 31,586 | 2,934 |
| 16 Apr 2026 | Sales | Off-plan | Villa · 3 B/R | 186.25 | 2,005 | 6,310,828 | 33,884 | 3,148 |
| 15 Apr 2026 | Sales | Off-plan | Villa · 3 B/R | 186.25 | 2,005 | 6,914,828 | 37,127 | 3,449 |
| 9 Mar 2026 | Sales | Off-plan | Villa · 3 B/R | 302.35 | 3,254 | 7,420,828 | 24,544 | 2,280 |
| 28 Jan 2026 | Sales | Off-plan | Villa · 3 B/R | 236.52 | 2,546 | 7,829,828 | 33,104 | 3,075 |
| 19 Jan 2026 | Sales | Off-plan | Villa · 4 B/R | 375.84 | 4,046 | 10,050,000 | 26,740 | 2,484 |
THE WATERCREST BY ELLINGTON: common questions
Is THE WATERCREST BY ELLINGTON delayed?
It is behind plan. Construction was 2.2% complete at the last DLD inspection on 24 July 2026, while its registered timeline (planned completion 31 March 2028) would expect about 47% by then.
When is the handover of THE WATERCREST BY ELLINGTON?
The planned completion date registered with Dubai Land Department is 31 March 2028. Handover usually follows completion; the developer confirms the exact date.
How much of THE WATERCREST BY ELLINGTON is built?
Construction was 2.2% complete at the last DLD inspection on 24 July 2026, as published by Dubai Land Department.
Where is THE WATERCREST BY ELLINGTON located?
THE WATERCREST BY ELLINGTON is in Wadi Al Safa 3, Dubai.
Who is the developer of THE WATERCREST BY ELLINGTON?
THE WATERCREST BY ELLINGTON is developed by ELLINGTON PROPERTIES DEVELOPMENT L.L.C (DLD developer no. 1117). It is registered with Dubai Land Department as project no. 3444.
Does THE WATERCREST BY ELLINGTON have an escrow account?
Yes. Dubai Land Department open data lists escrow account 1009766179. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in THE WATERCREST BY ELLINGTON?
The most recent sale registered with Dubai Land Department was on 13 July 2026 for AED 7,277,828. Across the 20 recorded sales, the average was AED 2,904 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.