photo: emaar.comUnder constructionDLD developer no. 1211 · EMAAR DEVELOPMENT P.J.S.C.
Deals checked 29 Oct 2026 · project details as of 17 Jul 2026
More from Emaar →Location
This project on Google
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 23 Oct 2026 | Mortgage | Off-plan | Villa · 4 B/R | 340.69 | 3,667 | 2,125,000 | 6,237 | 579 |
| 23 Oct 2026 | Sales | Off-plan | Villa · 4 B/R | 340.69 | 3,667 | 4,300,000 | 12,621 | 1,173 |
| 14 Oct 2026 | Sales | Off-plan | Villa · 4 B/R | 303.36 | 3,265 | 3,900,000 | 12,856 | 1,194 |
| 9 Oct 2026 | Mortgage | Off-plan | Villa · 4 B/R | 321.36 | 3,459 | 2,050,000 | 6,379 | 593 |
| 9 Oct 2026 | Sales | Off-plan | Villa · 4 B/R | 321.36 | 3,459 | 4,100,000 | 12,758 | 1,185 |
| 6 Oct 2026 | Sales | Off-plan | Villa · 4 B/R | 307.27 | 3,307 | 3,920,000 | 12,758 | 1,185 |
| 30 Sept 2026 | Mortgage | Off-plan | Villa · 4 B/R | 336.16 | 3,618 | 856,721 | 2,549 | 237 |
| 30 Sept 2026 | Mortgage | Off-plan | Villa · 4 B/R | 336.86 | 3,626 | 851,721 | 2,528 | 235 |
| 28 Sept 2026 | Sales | Off-plan | Villa · 5 B/R | 497.72 | 5,357 | 5,050,000 | 10,146 | 943 |
| 23 Sept 2026 | Sales | Off-plan | Villa · 5 B/R | 497.71 | 5,357 | 5,050,000 | 10,146 | 943 |
| 22 Sept 2026 | Sales | Off-plan | Villa · 5 B/R | 498.88 | 5,370 | 5,000,000 | 10,022 | 931 |
| 14 Sept 2026 | Mortgage | Off-plan | Villa · 4 B/R | 329.33 | 3,545 | 1,900,000 | 5,769 | 536 |
| 14 Sept 2026 | Sales | Off-plan | Villa · 4 B/R | 329.33 | 3,545 | 3,900,000 | 11,842 | 1,100 |
| 9 Sept 2026 | Mortgage | Off-plan | Villa · 4 B/R | 334.83 | 3,604 | 2,075,000 | 6,197 | 576 |
| 9 Sept 2026 | Sales | Off-plan | Villa · 4 B/R | 334.83 | 3,604 | 4,150,000 | 12,394 | 1,151 |
The Valley - Rivana: common questions
Is The Valley - Rivana delayed?
Not by DLD figures. Construction was 93.82% complete at the last DLD inspection on 5 August 2026, in line with or ahead of its registered timeline (about 82% expected by then, planned completion 31 March 2027).
When is the handover of The Valley - Rivana?
The planned completion date registered with Dubai Land Department is 31 March 2027. Handover usually follows completion; the developer confirms the exact date.
How much of The Valley - Rivana is built?
Construction was 93.82% complete at the last DLD inspection on 5 August 2026, as published by Dubai Land Department.
Where is The Valley - Rivana located?
The Valley - Rivana is in Al Yufrah 1, Dubai.
Who is the developer of The Valley - Rivana?
The Valley - Rivana is developed by EMAAR DEVELOPMENT P.J.S.C. (DLD developer no. 1211). It is registered with Dubai Land Department as project no. 2704.
Does The Valley - Rivana have an escrow account?
Yes. Dubai Land Department open data lists escrow account 4031221997653020. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in The Valley - Rivana?
The most recent sale registered with Dubai Land Department was on 23 October 2026 for AED 4,300,000. Across the 33 recorded sales, the average was AED 1,087 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.