The Valley - Kaiaphoto: emaar.comActive
Progress
19.13%
Handover
~ Jul 2028
Escrow
#10653441920051

The Valley - Kaia

#3405 · EMAAR DEVELOPMENT P.J.S.C. · Al Yufrah 1

More from Emaar
data last checked 17 Jul 2026

Construction progress

19.13% of construction complete · last inspected by DLD 9 Jun 2026

on pace — ≈18 pts behind the plan as of the last inspection

today
inspected 9 Jun 2026
start 28 Feb 2025 est. finish 31 Jul 2028