The Valley - Farm Grovephoto: emaar.comActive
Progress
10%
Handover
~ Dec 2028
Escrow
#4031221997653047

The Valley - Farm Grove

#3430 · EMAAR DEVELOPMENT P.J.S.C. · Al Yufrah 1

More from Emaar
data last checked 17 Jul 2026

Construction progress

10% of construction complete · last inspected by DLD 15 Jul 2026

≈26 pts behind the planned pace as of the last inspection

today
inspected 15 Jul 2026
start 28 Feb 2025 est. finish 31 Dec 2028