photo: emaar.comUnder constructionDLD developer no. 1211 · EMAAR DEVELOPMENT P.J.S.C.
Deals checked 29 Oct 2026 · project details as of 17 Jul 2026
More from Emaar →Location
This project on Google
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 23 Oct 2026 | Sales | Off-plan | Villa · 4 B/R | 317.53 | 3,418 | 3,375,000 | 10,629 | 987 |
| 24 Sept 2026 | Mortgage | Off-plan | Villa · 4 B/R | 276.11 | 2,972 | 1,801,445 | 6,524 | 606 |
| 7 Sept 2026 | Sales | Off-plan | Villa · 4 B/R | 364.02 | 3,918 | 3,752,888 | 10,310 | 958 |
| 27 Aug 2026 | Gifts | Off-plan | Villa · 4 B/R | 363.97 | 3,918 | 1,898,343.33 | 5,216 | 485 |
| 27 Aug 2026 | Sales | Off-plan | Villa · 4 B/R | 363.97 | 3,918 | 212,100 | 583 | 54 |
| 31 Jul 2026 | Sales | Off-plan | Villa · 3 B/R | 180 | 1,938 | 3,027,888 | 16,822 | 1,563 |
| 30 Jul 2026 | Gifts | Off-plan | Villa · 4 B/R | 293.9 | 3,164 | 3,320,000.2 | 11,296 | 1,049 |
| 16 Jul 2026 | Sales | Off-plan | Villa · 3 B/R | 180 | 1,938 | 3,027,888 | 16,822 | 1,563 |
| 27 Apr 2026 | Sales | Off-plan | Villa · 4 B/R | 363.99 | 3,918 | 3,751,880 | 10,308 | 958 |
| 23 Apr 2026 | Sales | Off-plan | Villa · 3 B/R | 208.22 | 2,241 | 3,317,888 | 15,935 | 1,480 |
| 22 Apr 2026 | Sales | Off-plan | Villa · 3 B/R | 180 | 1,938 | 3,072,888 | 17,072 | 1,586 |
| 25 Feb 2026 | Sales | Off-plan | Villa · 3 B/R | 187.57 | 2,019 | 3,111,888 | 16,591 | 1,541 |
| 4 Feb 2026 | Sales | Off-plan | Villa · 4 B/R | 311.98 | 3,358 | 3,839,888 | 12,308 | 1,143 |
| 29 Jan 2026 | Sales | Off-plan | Villa · 4 B/R | 352.92 | 3,799 | 3,720,888 | 10,543 | 979 |
| 9 Jan 2026 | Sales | Off-plan | Villa · 4 B/R | 332.21 | 3,576 | 3,699,888 | 11,137 | 1,035 |
The Valley - Elva: common questions
Is The Valley - Elva delayed?
Not by DLD figures. Construction was 25.86% complete at the last DLD inspection on 9 June 2026, in line with or ahead of its registered timeline (about 35% expected by then, planned completion 31 October 2028).
When is the handover of The Valley - Elva?
The planned completion date registered with Dubai Land Department is 31 October 2028. Handover usually follows completion; the developer confirms the exact date.
How much of The Valley - Elva is built?
Construction was 25.86% complete at the last DLD inspection on 9 June 2026, as published by Dubai Land Department.
Where is The Valley - Elva located?
The Valley - Elva is in Al Yufrah 1, Dubai.
Who is the developer of The Valley - Elva?
The Valley - Elva is developed by EMAAR DEVELOPMENT P.J.S.C. (DLD developer no. 1211). It is registered with Dubai Land Department as project no. 3462.
Does The Valley - Elva have an escrow account?
Yes. Dubai Land Department open data lists escrow account 0205345068535. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in The Valley - Elva?
The most recent sale registered with Dubai Land Department was on 23 October 2026 for AED 3,375,000. Across the 12 recorded sales, the average was AED 1,154 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.